Z ARCHIVE - D3 - Hwy 24 in Annandale: 2020 reconstruction
It’s been nine weeks since crews began work on Hwy 24 in Annandale. On Friday, June 12 the Hwy24/Oak Ave. and Park St. intersection will reopen to motorists.
Pleasant Ave. and Park St. intersection will close Friday, June 12 through Saturday, June 27. Motorists will use Oak Ave/Park St.
Hwy 24/Park St. remains detoured to through traffic in Annandale. Follow signs along Poplar Ave. and Hwy 55.
Stage two construction begins June 29
Crews will close and reconstruct Hwy 24/Oak Ave. from Hwy 55 to Park St. on Monday, June 29. Motorists will continue to use Poplar Ave. and Hwy 55.
Schedule is tentative and subject to change.
Hwy 24 Annandale detour map
For your safety and ours please stay out of work zones.
Annandale is open!
Access will be maintained and open to businesses and residents, however expect changes and gravel surfaces.
Stay connected
Visit the Hwy 24 Annandale project at www.mndot.gov/d3/projects/annandale.
For more information, contact Project Manager Mike Klasen, at michael.klasen@state.mn.us or 320-223-6615.
For 2020 roadwork projects on state highways in central Minnesota, visit www.mndot.gov/d3/construct and for current statewide traveler information, visit www.511mn.org.
Road work continues to be a critical service. MnDOT is committed to protecting the health, safety and well-being of its employees, contractors and all Minnesotans. Crews continue to follow the guidance of state and federal health officials to help prevent the spread of COVID-19.
|