Upcoming weekend closure of Lake St. and other closures on the horizon

Having trouble viewing this email? View it as a Web page.

MnDOT logo

no topic

In this update

Upcoming closures

  • Lake St. weekend closure July 13-16
  • Midtown Greenway closure July 17-20
  • 31st St. closure July 20-23
  • I-35W weekend closure July 27-30
  • 40th St. pedestrian bridge closure
  • 4th Ave. S/16th St. to westbound I-94 ramp closure

Upcoming events

  • 35W@94: Downtown to Crosstown Career Fair July 23

    As we move into mid-summer, we hope you are finding ways to stay cool, especially when traveling through the project area! There are some short-term local road and trail closures needed in the next week that will allow us to demolish the southbound lanes of the highway bridges over Lake St., the Midtown Greenway and 31st St. 

    Looking ahead, the 40th St. pedestrian bridge is scheduled to close at the end of the month, as is the 4th Ave S/16th St. ramp in downtown to westbound I-94. 

    And mark your calendars! If you’re interested in potential job opportunities with the project contractors, join us at a Career Fair on Mon, July 23!


    Lake St. weekend closure scheduled July 13-16

    We want to remind you that Lake St. is going to be closed this weekend between Stevens Ave. and 2nd Ave. S. starting at 10 p.m. tomorrow (Fri, July 13). We need to close Lake St. so we can safely demolish the southbound I-35W lanes of the highway bridge above the road. Construction activities at Lake St. and I-35W will be occurring 24 hours a day. The detour route will be to use Nicollet Ave, 31st St. and 3rd Ave S.

    The road will reopen by 5 a.m. on Mon, July 16. When Lake St. reopens, there will be lane and sidewalk reductions between Stevens Ave. and 2nd Ave. S.


    Midtown Greenway closure scheduled July 17-20

    The Midtown Greenway, between Nicollet Ave. and 5th Ave. S, will close starting at 6 a.m. Tue, July 17. The closure is needed for demolition of the southbound I-35W lanes of the highway bridge above the Midtown Greenway.

    During the closure, construction activities at the Midtown Greenway and I-35W will be occurring 24 hours a day. Residents and businesses in the area should expect some of this work to be disruptive, including noise and vibrations.

    The Midtown Greenway will reopen by 5 a.m. on Fri, July 20. Bicyclists and pedestrians should follow the posted detours.


    31st St. weekend closure scheduled July 20-23

    A weekend closure of 31st St. between Stevens Ave. and 2nd Ave. S. is scheduled to begin at 10 p.m. on Fri, July 20. The closure is needed to demolish the southbound I-35W lanes of the highway bridge above the road. Construction activities at 31st St. and I-35W will be occurring 24 hours a day. The detour route will be to use Nicollet Ave., Lake St. and 3rd Ave S.

    The road will reopen by 5 a.m. on Mon, July 23. When 31st St reopens, there will be lane and sidewalk reductions between Stevens Ave. and 2nd Ave. S.


      I-35W weekend closure scheduled July 27-30

      A weekend closure of I-35W is scheduled to start at 10 p.m. on Fri, July 27. I-35W will be closed between Hwy 280 and I-94. The closures are needed for two highway projects. The 35W@94 project will be working between I-94 and Hwy 62 doing utility crossings and demolishing the 40th St. pedestrian bridge. The I-35W Minneapolis to Roseville project will be resurfacing the road between Hwy 280 and I-94.

      The highway will reopen by 5 a.m. on Mon, July 30. The detour route is Hwy 62, Hwy 100 and I-694.


        40th St. pedestrian bridge closes July 27

        The 40th St. pedestrian bridge is also scheduled to close on Fri, July 27. The 40th St. pedestrian bridge will remain closed through fall 2020.

        We need to keep this bridge closed for so long for a couple reasons:

        • The bridge is being completely reconstructed and with all the construction activities taking place on I-35W for the remainder of the project, highway lanes will be reduced and shifted at various times.
        • Construction of the new bridge piers cannot begin until several stages of temporary traffic lanes on I-35W are completed below the bridge. 

          4th Ave. S/16th St. ramp to westbound I-94 closes late-July

          The downtown ramp from 4th Ave. S/16th St. to westbound I-94 is tentatively scheduled to close in late-July. Once the ramp closes it will remain closed for approximately two months. More details about the closure will be included in future updates.


          Join us!

          35W@94 Career Fair July 23

          MnDOT, Ames Construction, Lunda Construction Company and Shafter Contracting along with our subcontractors are hosting a career fair. We hope to see you there!

          Mon, July 23
          8 a.m.-12 p.m.
          Sabathani Community Center Gymnasium
          310 38th St. E, Minneapolis

          The career fair is an opportunity for community members to learn about job opportunities with the contractors and MnDOT.


          More about this project

          To learn more, including all current traffic impacts and detour routes, visit the project website at: www.mndot.gov/35w94

          Metro Transit bus routes will be impacted as a result of construction. For updated route information, and to sign up for Rider Alerts, visit: www.metrotransit.org/35W.

          Minnesota Valley Transit Authority routes will be impacted as a result of construction. For updated route information, visit: www.mvta.com.


          Stay Connected

          For real-time travel information anywhere in Minnesota visit: http://www.511mn.org/ or dial 5-1-1.