What is the crews' progress?
There are currently two crews working on Minnetonka Boulevard to complete construction efficiently.
One crew continues to replace the natural gas main along Minnetonka Boulevard, working to the west of Raleigh Avenue toward Salem Avenue. The main installation is anticipated to be complete by the end of next week, the week of November 25. At that time, a service crew will come on site to connect services to the new main.
The second crew is working on connecting existing mains to the newly completed main along Minnetonka boulevard. This will happen at most cross streets and is currently being done at the intersection of Ottawa Avenue South and Minnetonka Boulevard.
How can I contact CenterPoint Energy?
Check out our website for more details. If you have questions, please contact our Communication Specialist at 612-542-6198 or una.omeara@centerpointenergy.com. We appreciate your patience as we’re upgrading our infrastructure. We wish you a great season!
|