What is the crews' progress?
Service work is in progress in Lowry Hill East, with crews working on Hennepin Avenue between Emerson Avenue S. and 26th Street W. Hennepin Avenue W. is reduced to the middle two lanes of traffic at this time.
Service work includes moving inside meters outside by appointment and replacing and/or reconnecting service lines to the new main.
Beginning tomorrow, Oct. 29, 25th ½ Street W. will be closed as services are performed on that street.
Next week, beginning Monday Nov. 4, Emerson Avenue S. between Hennepin Avenue S. and 25th Street W. will be closed to traffic.
We anticipate construction to be complete in the next few weeks with restoration following approximately two weeks behind service crews. Check out our Restoration Practices webpage for more information.

How can I contact CenterPoint Energy?
Check out our website for more details and for updates on the crews’ progress. If you have questions, please contact our Communication Specialist at 612-542-6198 or una.omeara@centerpointenergy.com. We appreciate your patience as we’re upgrading our infrastructure. We wish you a great season!
|