What is the crews’ progress?
Natural gas service line and meter work
Throughout this week, crews continue to work on services along Cedar Lake Road and Mount View Avenue. Work is also being done on Russel Avenue S. and Queen Avenue S. between Mount View Avenue and Wayzata Boulevard.
Following completion of construction in those areas, crews will move to Vincent Avenue N. and Washburn Avenue N. between Glenwood Avenue and Chestnut Avenue W. Preparation is already being done on those streets for the coming construction.
If you have not had the chance to schedule an inside to outside meter move, please do so by calling 612-342-5123.
CenterPoint Energy’s authorized restoration contractor, Q3, will be following construction crews in the coming weeks.
How can I contact CenterPoint Energy?
Check out our website for more details and for updates on the crews’ progress. If you have questions, please contact our Communication Specialist at 612-321-5546 or una.omeara@centerpointenergy.com. We appreciate your patience as we’re upgrading our infrastructure. We wish you a great season!
|