What is the crews’ progress?
Natural gas main work
A crew from Michels Corporation, a CenterPoint Energy authorized contractor, is continuing to install natural gas mains in the Bryn Mawr neighborhood.
- In the week of Labor Day, the crew installed mains on the following streets: Mount View Avenue from Wayzata Boulevard to Penn Avenue S.; Russell Avenue S. from Mount View Avenue to Wayzata Boulevard; and Queen Avenue S. from Mount View Avenue to Wayzata Boulevard.
- This week, they plan to install mains on Mount View Avenue from Penn Avenue S. to Oliver Avenue S.; Cedar Lake Road from Sheridan Avenue S. to Penn Avenue S.; and Thomas Avenue S. from Cedar Lake Road to Wayzata Boulevard. “No parking” signs have been posted on both sides of Cedar Lake Road, the east side of Thomas Avenue S., and the north side of Mount View Avenue.
- In the week of Monday, September 16, they plan to install mains on Morgan Avenue S., Newton Avenue S., and Oliver Avenue S. between Laurel Avenue W. and Mount View Avenue.
- At a time to be determined, the crew will connect the new main on Queen Avenue S. to the existing intersecting main at Chestnut Avenue.
How can I contact CenterPoint Energy?
Check out our website for more details and for updates on the crews’ progress. If you have questions, please contact our Communication Specialist at 612-321-5546 or hannah.gullickson@centerpointenergy.com. We appreciate your patience as we’re upgrading our infrastructure. We wish you a great season!
|