What is the crews’ progress?
A crew from Michels Corporation, a CenterPoint Energy authorized contractor, has been replacing a natural gas steel main along the railroad between 85th Avenue NW and Osborne Road NE in Fridley. Their closure of 77th Avenue NE between the railroad tracks and Beech Street NE is scheduled to be completed Friday, June 21. They anticipate opening the road and pulling their detour signage that morning.
They anticipate that their remaining steel main installation will last into mid-July. Q3 Contracting, another CenterPoint authorized contractor, will follow to restore the areas affected by Michels Corporation’s work. They anticipate their work will last into late July.
How can I contact CenterPoint Energy?
Check out our website for more details and for updates on the crews’ progress. If you have questions, please contact our Communication Specialist at 612-321-5546 or hannah.gullickson@centerpointenergy.com. We appreciate your patience as we’re upgrading our infrastructure. We wish you a great season!
|