New gas main on 24th St. E. from Chicago Ave to Oakland Ave June 7 to 12

Having trouble viewing this email? View it as a Web page.

CenterPoint Energy Banner

June 6, 2024

Bookmark and Share

What is the crews’ progress for early June? 

From Friday, June 7 to Wednesday, June 12, a crew from Michels Corporation, a CenterPoint Energy authorized contractor, plans to install a natural gas main under the north sidewalk of 24th Street E. from Chicago Avenue S. to Oakland Avenue. During this time, traffic will remain open in each direction. Parking, the north sidewalk, and the bike lane will be closed on the north side of 24th Street E. The south sidewalk and south bike lane will remain open on the south side of 24th Street E.

 

After this stretch is done with the main installation, this crew will begin installing a main on 24th Street E. between Oakland Avenue and 5th Avenue S. More details will follow.

 

 

How can I contact CenterPoint Energy?

Check out the project’s web page for more details and for updates on the crews’ progress. If you have questions, please contact our Communication Specialist at 612-321-5546 or hannah.gullickson@centerpointenergy.com. We thank you for your patience as we’re upgrading our infrastructure!

 