CenterPoint Energy to replace natural gas lines in Plymouth this year

Having trouble viewing this email? View it as a Web page.

CenterPoint Energy Banner

April 4, 2024

Bookmark and Share

What is CenterPoint Energy doing?

Beginning on Monday, April 1 and lasting into early summer 2024, CenterPoint Energy’s authorized contractors will work along the following streets:

 

  • Black Oaks Lane N. from 26th Avenue N. to 30th Avenue N.​
  • Comstock Lane N. from 26th Avenue N. to 30th Avenue N.
  • Zanzibar Lane N. 26th Avenue N. to 29th Avenue N.
  • 26th Avenue N. from Dunkirk Lane N. to Zanzibar Lane N.
  • 27th Avenue N. from Comstock Lane N. to Black Oaks Lane N.
  • 27th Place N.
  • 28th Avenue N. from Comstock Lane N. to Zanzibar Lane N.
  • 29th Avenue N. from Dunkirk Lane N. to Zanzibar Lane N.
  • 30th Avenue N. from Comstock Lane N. to Black Oaks Lane N.

 

Equix Integrity updates our records on the locations of sewer lines in relation to natural gas lines. NPL will replace natural gas mains, move inside meters to the outside of homes by appointment, and replace or reconnect service lines as needed. Q3 Contracting will restore the areas affected by NPL’s work. There will be no assessment or cost associated with our work. During this time, parking or lane restrictions may occur.

 

What is the crews’ progress?

  • On Monday, April 8, a crew from NPL will begin CenterPoint Energy’s natural gas line project in Plymouth. Their first task is replacing the project’s natural gas mains. They will start on 30th Avenue N. and work from Black Oaks Lane N. to Comstock Lane N. Afterward, they will replace the main on Comstock Lane N. from 30th Avenue N. to 26th Avenue N.
  • They anticipate finishing all the project’s natural gas work within the month of April. This includes replacing the rest of the project’s natural gas mains, moving inside meters outside by appointment, and replacing and/or reconnecting the service lines to the new mains. They anticipate beginning the meter and service line work in mid-April.
  • During this time, traffic impacts will be minimal. Drivers may see traffic signs on Dunkirk Lane N.

 

 

How can I contact CenterPoint Energy? 

Check out our website for more details and for updates on the crews’ progress. If you have questions, please contact our Communication Specialist at 612-321-5546 or hannah.gullickson@centerpointenergy.com. We thank you for your patience as we’re upgrading our infrastructure!

 

CNP Map of Plymouth 2024