Construction is 41 percent complete on Winnetka Pipeline project

Having trouble viewing this email? View it as a Web page.

CenterPoint Energy Banner

July 18, 2017

Bookmark and Share

 What is CenterPoint Energy doing for construction?


Crews from CenterPoint Energy began replacing an existing natural gas pipeline in Brooklyn Park on Monday, May 8. Project construction in Brooklyn Park is expected to last until early August. Michels Corporation, an authorized CenterPoint Energy contractor, have been installing natural gas distribution and transmission mains along 68th and 69th Avenues N. from Winnetka Avenue N. eastward to Adair Avenue N. A New Hope/Crystal phase will begin early August 2017 on Winnetka Avenue N. southward from 68th Avenue N. to 55th Avenue N. and on 62nd Avenue N. westward from Winnetka Avenue N. to W. Broadway Avenue. (See the map below.)



What is the crews' progress?


  • Construction on the Winnetka Pipeline project is 41 percent complete.

 

  • Within the weeks of July 17 and 24, the crews from Michels Corporation will finish work along 68th and 69th Avenues N. from Adair Avenue N. to Winnetka Avenue N. This work will conclude the Brooklyn Park phase of construction.

 

  • During this time, crews from Q3, an authorized contractor for CenterPoint Energy, will restore the blacktop areas affected by construction along 68th and 69th Avenues N.


  • As crews from Q3 restore one intersection at a time along 68th and 69th Avenues N., that intersection will be closed briefly during one day; then the intersection will be reopened when the blacktop area is fully restored. This will continue along 68th and 69th Avenues N. until the intersections are complete.

 

  • Starting the week of July 31, the crews will begin the New Hope and Crystal phase of construction. The crews will be installing natural gas pipeline along Winnetka Avenue N., starting from the north end of the project at 68th Avenue N. working south to 55th Avenue N. 




How can I contact CenterPoint Energy?


For questions about the project, please call our Information Hotline at 612-321-5369 or our Communication Specialist at 612-321-5546. For questions about restoration (hard or soft surfaces) please call our Restoration Department at 612-321-5042. ​CenterPoint Energy wants to thank you for your patience. 

 

Please visit our website often to receive project updates, traffic alerts and anticipated completion dates. Thank you.

 

Winnetka Pipeline