Downtown Waconia Reconstruction - Aug. 2, 2024

Project Update

Map of project area

Work completed this week (7/29)

  • Boulevard grading was completed in Stage 1.
  • Utility work continued in Stage 2.

Work planned for next week (8/5)

  • Utility work is anticipated to be completed in Stage 2.
  • Street excavation and grading will begin on Main St. and Elm St. in Stage 2.
  • Sod may be installed in Stage 1 the week of Aug. 12. Notices about proper care for the new sod will be sent out to properties the week of installation.

Access

Properties will have access to driveways and alleys at the end of each day. During the workday, best efforts will be made to accommodate regular access as much as possible. Please contact our on-site project representative, Colin Quinn at 763-349-4450, with any questions, property specific needs, and accommodations.


Thank you for your patience and cooperation as we construct these important improvements!