Holtmeier will finish pavement removals on Gorman Street, 4th Street, and 9th Street starting today. The grading crew started to tolerance the gravel on Gorman Street from 7th Street to 5th Street in preparation of paving. The grading crew will continue prepping Gorman Street and the 1st Street Area early this week. We kindly ask that residents park on a side street during working hours while this work is being performed. Paving on these streets is tentatively scheduled for the end of this week.
Holtmeiers underground crew should finish utilities along 4th Street from Galbraith Street to Gorman Street and Gorman Street from 4th Street to 2nd Street by the end of this week. Once these areas are complete, the grading crew will begin restoring these streets.