Baxter Inglewood Drive Improvements Update

Having trouble viewing this email? View it as a Web page.

Baxter

August 5, 2022

2022 Foley Road, Isle Drive and Forthun Improvements Project

Upcoming work

Week of August 8

  • Continue sanitary sewer and watermain work along Foley Road.
  • Sanitary sewer is expected to be complete. Watermain will be complete by the end of August.
  • Bituminous paving on Isle Drive and Forthun Road will take place on Tuesday and Wednesday (August 9 and 10).
  • Grading and topsoil placement along curbs will continue.
  • Light pole bases are expected to be installed next week.

For more information, click here to view the latest project newsletter.