Perry St. between 106th, 104th Aves. closes Monday for water main work

Perry St. closure - Holland Twp.

WHEN: May 24, 2021 through July 23, 2021

WHERE: Perry St., between 104th Ave. and 106th Ave., Holland Twp.

WHY: Water Main Work

BACKGROUND: Perry Street, between 104th Avenue and 106th Avenue in Holland Township, will be closed beginning Monday, May 24, 2021, for a permitted water main project being conducted by Holland Township. The project is expected to run through July 23, 2021. Please note that all dates are tentative and work is weather dependent.

DETOUR: The planned detour for this project is 104th Avenue/M-121/106th Ave.


72nd Ave. to close between Blair, Tyler streets for culvert replacement work

Road Closed Barricade

WHEN: Starting on Monday, May 24, 2021

WHERE: 72nd Ave., between Tyler St. and Blair St.

WHY: Culvert Replacement

BACKGROUND: On Monday, May 24, 2021, the Ottawa County Road Commission (OCRC) will begin a culvert replacement project on 72nd Avenue between Tyler Street and Blair street in Blendon/Olive townships.

This closure is expected to last until Tuesday, May 25, weather permitting.


Road Closures:

TOWNSHIP

STREET

SEGMENT

REASON

RESPONSIBLE AUTHORITY

DURATION

Chester

32nd Ave.

Coolidge St. to Gooding St.

Bridge Replacement

OCRC

TBD

Holland

Paw Paw Dr./104th Ave.

Intersection

Water Main

Township

April 14-June 7

Georgetown

48th Ave.

Fillmore St. to Bauer St.

Culvert

OCRC

May 17-June 4

Blendon

72nd Ave.

Blair St. to Tyler St.

Culvert

OCRC

May 24-25

Park

Lilac Ave.

James St. to Vanessa Ave.

Sewer

Permit

May 24-25

Holland

Perry St.

104th Ave. to
106th Ave.

Water Main

Township

May 24-July 23

 

Road Resurfacing:

TOWNSHIP

STREET

SEGMENT

EST. DURATION

Grand Haven

Lakeshore Dr.

Fillmore St. to Buchanan St.

May 17-June 5

Note: Resurfacing does not close the road. It will remain open to through traffic, with temporary lane closures.


Remember: Drive safe and stay alert in work zones!