WHAT: Gravel Road Reconstruction
WHERE: 40th Ave.
TOWNSHIP: Jamestown
START DATE: Monday, August 3, 2020
ESTIMATED COMPLETION DATE: Friday, October 2, 2020
PROJECT DETAILS: The Ottawa County Road Commission, in conjunction with Jamestown Township, will be reconstructing 40th Avenue from the county line to Adams Street. The existing gravel road will be reconstructed to a paved road.
The project is expected to begin on Monday, August 3, and be completed by Friday, Oct. 2. Note that all dates are tentative, and work is weather-dependent.
TRAFFIC IMPACT: 40th Avenue will be closed to through traffic between the county line and Adams Street during this project, with access being maintained for those living within the construction limits.
WHAT: Road Closure
WHERE: 28th Ave., Baldwin St. to Bauer Rd.
TOWNSHIP: Georgetown
START DATE: Monday, August 3, 2020
ESTIMATED COMPLETION DATE: Friday, August 14, 2020
PROJECT DETAILS: 28th Avenue in Georgetown Township will be closed between Baldwin Street and Bauer Road Aug. 3-14 for permitted water crossing work.
Note that all dates are tentative, and work is weather-dependent.
Road Closures:
| Township: |
Road: |
Segment: |
Work:
|
Est. Finish: |
| Tallmadge |
Luce/Linden St. |
M-45 to 20th Ave. |
Bank Erosion Repair |
TBD |
| Georgetown |
48th Ave. |
North of Fillmore St. |
Cross Culvert |
Aug. 7 |
| Allendale/Polkton |
68th Ave. |
Leonard St.-M-45 |
Bridge Rehab |
Aug. 14 |
| Holland |
Lakewood Blvd. |
River Ave. Intersection |
Water Main |
Aug. 7 |
| Allendale |
68th Ave. |
At Pingree St. |
Cross Culvert |
Aug. 7 |
| Georgetown |
28th Ave. |
Baldwin St. to Bauer Rd. |
Water Crossing |
Aug. 14 |
| Jamestown |
40th Ave. |
Adams St. to county line |
Reconstruction |
Oct. 2 |
| Georgetown |
Port Sheldon St. |
40th Ave. to 48th Ave. |
Reconstruction |
Oct. 23 |
Street Resurfacing:
| Township: |
Road: |
Segment:
|
Est. Finish: |
| Grand Haven |
Lakeshore Dr. |
Rosy Mound Dr. to Buchanan St. |
Aug. 10 |
| Georgetown |
14th Ave./Port Sheldon St. |
44th St. to Main St. |
Aug. 15 |
| Jamestown |
Riley St. |
32nd Ave. to 8th Ave. |
Aug. 15 |
| Jamestown |
Adams St. |
48th Ave. to 24th Ave. |
Aug. 15 |
Subdivision Street Resurfacing:
| Township: |
Est. Finish: |
| Holland |
August 14 |
Upcoming Construction Projects:
| Township: |
Road: |
Segment:
|
Work:
|
Est. Start: |
| Jamestown |
Adams St. |
48th Ave. to 24th Ave. |
Resurfacing |
Late July |
Note: Resurfacing does not close the road. It will remain open to through traffic, with temporary lane closures.
Please note that all dates are tentative and subject to change.
|