Road Closures:
| Township: |
Road: |
Segment: |
Work:
|
Est. Finish: |
| Tallmadge |
Luce/Linden St. |
M-45-20th Ave. |
Bank Erosion Repair |
TBD |
| Allendale/Polkton |
68th Ave. |
Leonard St.-M-45 |
Bridge Rehab |
July 31 |
| Georgetown |
Port Sheldon St. |
40th Ave. to 48th Ave. |
Reconstruction |
Oct. 23 |
Street Resurfacing:
| Township: |
Road: |
Segment:
|
Est. Finish: |
| Chester |
Wilson St. |
40th Ave. to 24th Ave. |
July 17 |
| Grand Haven |
Lakeshore Dr. |
Rosy Mound Dr. to Buchanan St. |
Aug. 10 |
| Georgetown |
14th Ave./Port Sheldon St. |
44th St. to Main St. |
Aug. 15 |
| Blendon |
72nd Ave. |
New Holland St. to Port Sheldon St. |
July 20 |
| Park |
Lakeshore Dr. |
Riley St. to Lakewood Blvd. |
July 20 |
Subdivision Street Resurfacing:
| Township: |
Est. Finish: |
| Holland |
July 31 |
Upcoming Construction Projects:
| Township: |
Road: |
Segment:
|
Work:
|
Est. Start: |
| Jamestown |
40th Ave. |
County Line to Adams St. |
Gravel Road Reconstruction |
Mid July |
| Jamestown |
Riley St. |
32nd Ave. to 8th Ave. |
Resurfacing |
Late July |
| Jamestown |
Adams St. |
48th Ave. to 24th Ave. |
Resurfacing |
Late July |
Note: Resurfacing does not close the road. It will remain open to through traffic, with temporary lane closures.