Port Sheldon St. reconstruction from 48th to 40th Aves. in Georgetown Twp. starts July 6

WHAT: Road Reconstruction

WHERE: Port Sheldon St.

TOWNSHIP: Georgetown

START DATE: Monday, July 6, 2020

ESTIMATED COMPLETION DATE: Friday, October 23, 2020

PROJECT DETAILS: Port Sheldon Street from 48th Avenue to 40th Avenue will be reconstructed. The existing 2 lane road will be reconstructed to a 3 lane road with paved shoulders, concrete curb and gutter, and storm sewer.

The project is expected to begin on Monday, July 6, and be completed by Friday, Oct. 23. Note that all dates are tentative, and work is weather-dependent.

TRAFFIC IMPACT: Port Sheldon Street be closed to through traffic during this project, with access being maintained for those living within the construction limits. The detour will consist of 48th Avenue/Baldwin Street/36th Avenue.

Port Sheldon Reconstruction Map

Road Closures:

Township: Road: Segment: Work:
Start & Est. Finish:
Tallmadge Luce/Linden St. M-45-20th Ave. Bank Erosion Repair May 18-TBD
Allendale/Polkton 68th Ave. Leonard St.-M-45 Bridge Rehab June 8-July 31
Georgetown Port Sheldon St. 40th Ave. to 48th Ave. Reconstruction July 6-Oct. 23

 

Street Resurfacing:

Township:  Road: Segment:
Start & Est. Finish:
Georgetown Port Sheldon St./44th Ave. Chicago Dr. to 8th Ave. June 15-July 10
Grand Haven Lakeshore Dr. Rosy Mound Dr. to Buchanan St. June 29-Aug. 10
Blendon 72nd Ave. New Holland St. to Port Sheldon St. July 10-July 20
Park Lakeshore Dr. Riley St. to Lakewood Blvd. July 13-July 20

 

Subdivision Street Resurfacing:

Township: Est. Finish:
Chester July 10
Holland July 31

Upcoming Construction Projects:

Township:  Road: Segment:
Est. Start:
Chester Wilson St. 40th Ave. to 24th Ave. July

Note: Resurfacing does not close the road. It will remain open to through traffic, with temporary lane closures.

Please note that all dates are tentative and subject to change.


OCRC holiday closure reminder

OCRC July 3 Closed