Road Commission Construction Update: May 4
Ottawa County, Michigan sent this bulletin at 05/04/2018 02:25 PM EDT
Road Commission Construction Update: May 4, 2018
Read below to find out all about our current and upcoming construction projects and closures.
You can view all of our construction projects for the season at: http://www.ottawacorc.com/construction-projects/
You can also view all of our current and upcoming construction projects and road closures on our Interactive Road Work Map: http://www.ottawacorc.com/construction-map/

Current-Road Resurfacing Item I:
| Road Name: | Timeline: |
| Georgetown Subdivisions (Complete list on our website: www.ottawacorc.com/construction-projects) | April 30-June 15 |
| Quincy Street, from 22nd Ave. to County Line | May 3- April 15 |
Upcoming- Resurfacing Item II:
Resurfacing on Item II is scheduled to begin in two weeks, specific dates will be announced next week.
| Road Name: | Timeline: |
| Holland Subdivisions (Complete list on our website: www.ottawacorc.com/construction-projects) | TBA |
| Ransom St. from 124th to 120th Ave. | TBA |
Resurfacing does not close the road, it will remain open to through traffic, with lane closures.
Road Closures:
| Road Name and Limits: | Timeline: |
| 136th Ave.- Quincy St. to New Holland St. | May 1- May 11 |
| 84th Ave.- Riley St. to Quincy St. | May 1-May 13 |
| Rosy Mound Dr.- US-31 to Lakeshore Dr. | April 30-May 6 |
| Lincoln St.- 144th Ave. to US-31 | April 16-June 3rd |
| Tyler St.- 72nd Ave. to 80th Ave. | Feb. 21- Until Further Notice |
Cottonwood Dr. Reconstruction:
The Road Commission is still waiting for a start date from the contractor for the project. Utility installation has begun, and the tree cutting for the widening of the road is completed. The reconstruction is expected to begin in May. You can find the most up to date information as it becomes available on our website: www.ottawacorc.com/cottonwooddriveproject/
Remember to drive safe and stay alert in work zones!

If you have any questions about the information in this release, please email Zach Russell, Communications Administrator for the Ottawa County Road Commission: zrussell@ottawacorc.com