Construction Update for September 5, 2025

view as a webpage | Bookmark and Share

September 5, 2025

Construction Update

Village of Milford Logo

The following is an update on the current construction projects within the Village of Milford as of September 5, 2025. Information on construction projects may be found at villageofmilford.org/roads

Projected dates and timelines are all weather permitting. Residents directly adjacent to construction zones will have informational flyers distributed throughout the project duration.

 

Family Drive Water Main Connection Project

Stormwater drainage work on Highland Ave. is scheduled to wrap up this week. Testing of the new water main is ongoing and pipe will be connected at the treatment plant and wellsite upon completion of the testing. Concrete and asphalt paving will follow in the coming weeks.

Access to the Milford Trail via sidewalk remains closed to pedestrians along Commerce Rd. west of Highland Ave. and alternate routes are required. The trailhead at Family Drive remains open via the parking lot only.