Construction Update for October 4, 2024

view as a webpage | Bookmark and Share

October 4, 2024

Construction Update

S. Main St. - Paved

The following is an update on the current construction project within the Village of Milford as of October 4, 2024.

Information on construction projects may be found at villageofmilford.org/roads

Projected dates and timelines are all weather permitting.

 

2024 Road Project - S. Main Street

This week, Artisan Contracting completed structure adjustments in both the northbound and southbound lanes of S. Main Street. Restoration and irrigation system repairs are slated to be completed by weeks end.

Structure adjustments in the center lane of S. Main Street are scheduled for next week, followed by any minor punch list items.

All work is weather permitting.