Construction Update

S. Main Update

The following is an update on the current construction project within the Village of Milford as of September 13, 2024. Information on construction projects may be found at villageofmilford.org/roads

Projected dates and timelines are all weather permitting.

 

2024 Road Project - S. Main Street

The contractor has completed all the curb and gutter work on the west side of S. Main Street.  The edge of metal asphalt repairs will continue next week, including necessary repairs in front of driveways. All residents will be notified of when they will need to be out of their driveways by the on-site inspector .

The contractor will also work next week on completing sidewalk replacements on the west side of S. Main Street.  Asphalt milling and paving is scheduled to start the week of September 23 with several roads being closed at S. Main Street during operations. Please expect long delays and avoid the area if possible. 

All work is weather permitting. Residents directly impacted by the road work will be notified about parking requirements during concrete curing.