Construction Update for August 30, 2024

view as a webpage | Bookmark and Share

August 30, 2024

Construction Update

S Main Construction Project

The following is an update on the current construction project within the Village of Milford as of August 30, 2024. Information on construction projects may be found at villageofmilford.org/roads

Projected dates and timelines are all weather permitting.

 

2024 Road Project - S. Main Street

The curb and gutter replacement on the east side of S Main Street has been completed and edge of metal asphalt repairs have been started.  Artisan Contracting will continue working on the east side with the asphalt edge repairs and the limited sidewalk replacements. 

Next week, work will begin on the west side of S Main Street with curb and gutter removal/replacement, as well as asphalt edge repairs and sidewalk replacement.

All work is weather permitting. Residents directly impacted by the road work will be notified about parking requirements during concrete curing.