November 4, 2022
The following is an update on current and upcoming construction projects within the Village of Milford as of November 4, 2022. Projected dates and timelines are all weather permitting.
2022 Paving & E. Huron Projects
Punch list items remain and will be addressed in the coming weeks.
2022 Commerce Rd. Project
Concrete work is complete. Asphalt paving is tentatively scheduled for Monday, November 7th, weather permitting. Restoration and landscaping will follow in the upcoming weeks.
W. Commerce Road will be closed to vehicular and pedestrian thru traffic for the duration of the project.
The preconstruction meeting recording, presentation, and FAQs are available at www.villageofmilford.org/roads.
|
|