The following is an update on current and upcoming construction projects within the Village of Milford as of July 22, 2022. Projected dates and timelines are all weather permitting.
E. Huron St. Project
Asphalt paving of the roads north of Huron (Fairview, S. Houghton, Franklin, and Mont Eagle) was completed yesterday. Topsoil placement and restoration on these streets will take place beginning early next week. Huron and S. Houghton are scheduled to be paved Wednesday, July 27th, weather permitting. The River Drive & Huron Street intersection will be closed during these paving operations.
Huron Street remains closed to thru traffic for the duration of the project.
2022 Road Paving Project
Roadwork in the Milford Heights subdivision is scheduled to start August 1st, weather permitting. Notices will be distributed to all residents impacted by construction.
Work in the Milford Bluffs neighborhood will follow.
The pre-construction meeting recording and presentation are available at www.villageofmilford.org/roads.
|
|