Construction Update for July 1, 2022

view as a webpage | Bookmark and Share

July 1, 2022

Construction Update

Concrete curb being poured in a roadway

The following is an update on current and upcoming construction projects within the Village of Milford as of July 1, 2022. Projected dates and timelines are all weather permitting.

 

E. Huron St. Project

Concrete sidewalk and aggregate base placement are completed. Asphalt paving is tentatively scheduled to start the week of July 5th. Flyers will be distributed to residents impacted by paving operations.

Please do not touch or walk/ride on newly poured concrete as footprints, tire marks, and writing can result in future issues with sidewalks and may require damaged sections to be removed and replaced. This leads to additional costs and delays to other scheduled work.

Huron Street remains closed to thru traffic for the duration of the project.

2022 Road Paving Project

The 2022 Road Paving Project (Milford Heights & Milford Bluffs neighborhoods) will start following the conclusion of the E. Huron project, later in July. The pre-construction meeting recording and presentation are available at www.villageofmilford.org/roads.