April 22, 2022
The following is an update on current and upcoming construction projects within the Village of Milford as of April 22, 2022. Projected dates and timelines are all weather permitting.
E. Huron St. Project
Sidewalk work has started on Huron Street and will continue next week. Please do not touch or walk/ride on newly poured concrete as footprints, tire marks, and writing can result in future issues with sidewalks and require damaged sections to be removed. These removals can lead to additional costs and delays to other scheduled work.
Preparations for road grading and curb placement will begin next week. Gas main replacement is scheduled for next week, weather dependent.
Huron Street remains closed to thru traffic for the duration of the project.
|
|