M-26 detour to start April 25 for Silver River bridge replacement in Keweenaw County
Michigan DOT sent this bulletin at 04/19/2023 02:50 PM EDT
Having trouble viewing this email? View it as a Web page. |
FOR IMMEDIATE RELEASE MEDIA CONTACT
April 19, 2023 Dan Weingarten
906-250-4809
WeingartenD@Michigan.gov
M-26 detour to start April 25 for Silver River bridge
replacement in Keweenaw County
EAGLE HARBOR, Mich. – A complete closure and detour of M-26 over the Silver River between Eagle Harbor and Copper Harbor will begin April 25 as part of a $2.9 million Michigan Department of Transportation (MDOT) investment to remove and replace the bridge this summer.
County:
Keweenaw
Highway:
M-26
Closest town:
Eagle Harbor
Start date:
Tuesday, April 25, 2023
Estimated end date:
July 2023
Traffic restrictions:
During the project, traffic will be detoured for approximately 10 weeks via a posted route on US-41. The M-26 closure will be just west of the western entrance to Brockway Drive, about 10 miles from Copper Harbor.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 35 jobs.
Safety benefit:
This work will replace a bridge which has reached the end of its useful service life. The roadway section of the new bridge will be wider, including 12-foot lanes and 8-foot shoulders, providing more space and increased safety for bicyclists and pedestrians.
###
Driving safely in work zones saves lives!
Protect MI work zones by taking the pledge.