Rebuilding Michigan: I-496 project scheduled to be complete Nov. 10

COUNTIES:                             
Eaton

Ingham

 

HIGHWAY:                                   

I-496

 

CLOSEST CITY:   
Lansing

 

PROJECT ESTIMATED REOPEN DATE:

4 p.m.

Tuesday, Nov. 10, 2020

 

PROJECT:  
The Michigan Department of Transportation (MDOT) has invested approximately $60 million to improve I-496 between I-96 and Lansing Road. The westbound, and final, portion of the I-496 Pave the Way project will reopen to traffic on Tuesday, Nov. 10.

 

This was the first of 122 projects throughout the state made possible by Gov. Gretchen   Whitmer's Rebuilding Michigan initiative allowing the department to advance projects and complete them more quickly than with cash financing only. 

 

Project map

 

For more information about the project, go to www.Michigan.gov/496Lansing.

TRAFFIC RESTRICTIONS:
Westbound I-496 will be open to traffic on Tuesday afternoon.

SAFETY BENEFITS:
These improvements will provide increased safety and mobility in this area of the I-496, which is a significant local and national trade corridor.

###