Final stage of US-131 reconstruction in Three Rivers begins Monday
Michigan DOT sent this bulletin at 10/01/2020 01:15 PM EDT
|
|
Having trouble viewing this email? View it as a Web page. |
Starting Monday, Oct. 5, crews will begin the final stage of US-131 reconstruction in Three Rivers, St. Joseph County. Traffic will be in the right lanes of northbound and southbound US-131 while construction is completed on the median and Michigan-left turn lanes.
Construction still is expected to be completed by Sunday, Nov. 15. Until then, left turns will be open as construction allows.
No left turns or through-traffic will be permitted at Coon Hollow Road and Arnold Street. Because of the new median on US-131, those roads will be right-turn only; Coon Hollow Road to southbound US-131, and Arnold Street to northbound US-131.
For project details and a map, visit Mi Drive.