Michigan DOT sent this bulletin at 08/27/2019 12:19 PM EDT
|
|
Having trouble viewing this email? View it as a Web page. |
FOR IMMEDIATE RELEASE TUESDAY, AUGUST 27, 2019
CONTACT: John Richard, MDOT Office of Communications, 616-262-1565
RichardJ2@Michigan.gov
Mid-October completion for
M-66 project near Lake Odessa
COUNTY:
Ionia
HIGHWAY:
M-66
CLOSEST CITY:
Lake Odessa
START DATE:
Tuesday, May 28, 2019
ESTIMATED END DATE:
Tuesday, Oct. 15, 2019
PROJECT DETAILS:
The Michigan Department of Transportation (MDOT) is investing approximately $11.4 million to resurface M-66 from M-50 north to I-96. The project also includes new concrete curb and gutter, joint replacements, new culverts, improved drainage, and new guardrail.
After the project started, poor soils and drainage issues impacted construction, making additional shoulder reconstruction and drainage work necessary. This changed the estimated end date of Aug. 31 to mid-October.
Project flyer: https://tinyurl.com/y3se6994
Project map: https://tinyurl.com/y5cnt7uv
Southbound M-66 will remain open for the remainder of the project. Northbound M-66 will be closed and detoured west on M-50, north on Jordan Lake Road and east on Portland Road.
SAFETY BENEFITS:
This project will improve the ride quality and extend the service life of the roadway.
###
When you see barrels, people are fixing your roads. Drive like you work here. www.Michigan.gov/WorkZoneSafety www.twitter.com/MDOT_West | www.facebook.com/MichiganDOT | www.youtube.com/MichiganDOT