Hancock project update: US-41 traffic shifts, M-26 ramp opens Monday

 
MDOT E-mail MDOT on facebook MDOT on Twitter MDOT on YouTube Mi Drive - Know before you go. MDOT on Instagram Sign up for E-mails form MDOT

Having trouble viewing this email? View it as a Web page.

Bookmark and Share

FOR IMMEDIATE RELEASE                                THURSDAY, JUNE 15, 2017 
CONTACT: Dan Weingarten, MDOT Office of Communications, 906-250-4809
                     weingartend@michigan.gov

 

 

US-41 traffic shifts, M-26 ramp opens Monday
as part of Hancock project

Safety features:
- A speed limit of 25 mph in the US-41 Hancock work zone is in place.
- Closing US-41 lanes provides workers with safe, protected work zones and provides motorists with the safest route possible through the area.

June 15, 2017 -- Motorists will see a new traffic pattern at the Michigan Department of Transportation's (MDOT) US-41 reconstruction project in Hancock beginning June 19.

            Beginning Monday, all US-41 (Front Street) traffic will shift to the southbound lanes of the highway, maintaining one lane in each direction on Front Street between the Portage Lake Lift Bridge and Reservation Street. The southbound US-41 connector ramp to eastbound M-26 toward Ripley will be reopened. Work will commence on the northbound lanes of US-41. Northbound US-41 traffic will now cross the median as it exits the lift bridge.

            Traffic from Ripley to Houghton will be detoured through Hancock along a posted detour route. Traffic from Hancock to Ripley will now proceed normally. The sidewalk on the north side of US-41 will be closed and the south sidewalk will be reopened.

             To reduce bridge operation and limit delays, a 13-foot, 6-inch height restriction for vehicles is being imposed on the Portage Lake Lift Bridge from 7 to 9 a.m. and from 10:30 a.m. to 7 p.m. each day. These restrictions run through July 28. A 12-foot width restriction is also in effect in the work zone.

            MDOT is completing the reconstruction of US-41 in Hancock, which began in 2016. In the final phases of the project, MDOT will invest $2 million to reconstruct Front Street between Reservation Street and the Portage Lake Lift Bridge, as well as the southbound US-41 connector ramp to eastbound M-26.
            Project map: https://goo.gl/UeV6kL

###

Download MDOT's Mi Drive traffic information app: www.michigan.gov/drive 