South Seventh and Greenview Aug. 29 Project Update
City of Ann Arbor, MI sent this bulletin at 08/29/2024 03:27 PM EDTResidents of the South Seventh and Greenview area,
No work will be performed from 3 p.m. Friday Aug.30, until 7 a.m. on Tuesday Sept. 3 due to the Labor Day holiday on Monday, Sept. 2.
Here is an update on each road in the project:
South Seventh:
The final course of asphalt will be paved from Scio Church to Delaware on Friday, Aug. 30, weather permitting. The road will be completely closed to traffic from 7 a.m. to about 5 p.m. Please use alternate routes during those times.
Although it’s close, South Seventh Street is not complete. Paving, utility cover adjustments and crosswalk markings remain to be done. While South Seventh Street is open to vehicles, please continue to drive slowly as workers are present and children have returned to school.
- Past: Underground work is complete, and the first layer of asphalt was paved. The road was opened to traffic for the start of the school year, as promised.
- Present: This week, grass restoration was performed. Topsoil was placed in the disturbed areas of the right-of-way and hydroseeded. This will be maintained and watered by the contractor until established. The road will be paved on Friday, Aug. 30.
- Future: Following paving, utility covers in the road will be adjusted to the surface and a round, concrete collar placed around them; cones will be in place until they are cured enough to drive on. This will be done in stages to keep the road open to traffic. The final step will be pavement markings which will include some markings in the Scio Church/South Seventh intersection and crosswalks at Scio Church, Braeside, Lans Way, Greenview and Delaware.
After the contractor is complete:
- The city will add and adjust any permanent signs and add the sensors for the Scio Church traffic signal.
- The city’s Forestry staff will evaluate the new lawn extension for any viable locations for new trees.
- DTE will move the power pole near the school and replace the sidewalk with an 8-foot-wide sidewalk after Labor Day
- DTE will add streetlights to illuminate all the crosswalks (no date available on when these will be installed).
- The city will gather traffic and speed data next spring.
South Greenview:
- Past: The watermain is complete. Curb removals and road grading has commenced.
- Present: The road is being graded and backfilled with stone. As with South Seventh Street, the unsuitable soils will be removed and replaced with stone to increase the longevity of the road.
- Future: The curb area and road will be graded to prepare for concrete and paving. Stone will be left on the south side of the road to maintain a drivable surface. Curb and driveways will be poured after Labor Day, you will get a notification on when and how long driveways will not be accessible. Paving is planned for mid-September.
North Greenview:
- Past: Storm detention was installed between Scio Church and Barnard. Stormwater detention work between Normandy and Avondale has begun.
- Present: The detention system and the catch basins on the side streets were installed this week. All the stormwater pipe work should be complete by Tuesday, Sept. 2 at the latest. This will be the last of the underground work.
- Future: Next week, curb and driveway removals and road grading will begin. Stone will be ramped for access to driveways until they are replaced with new concrete. Road grading will last at least one month. The entire stretch of North Greenview will be paved at the same time, instead of completing it in sections. This will result in a better finished product.
Soil stability testing will continue on North Greenview. If ‘bad’ soil is found, it will be cut out and replaced with stone. We anticipate tests will result in the need to undercut most of the road. This will extend the project time before paving; however, the project is on track to be completed by November.
Thank you,