Wiscasset Route 1 Downtown Update: 11/28/2018
MaineDOT sent this bulletin at 11/28/2018 03:05 PM ESTHaving trouble viewing this email? View it as a Web page. | You are subscribed to Wiscasset Downtown Improvements |
Wiscasset Route 1 Downtown Update: 11/28/2018
Wiscasset Suspending Work for the Year
- Winter shutdown is scheduled for December 7th.
- The startup date in the spring is anticipated to be April 15th, 2019. The completion date for the project is still expected to be October 19th, 2019.
- Work to be completed will include excavation, gravel, paving, curbing, lighting, traffic signals, brick sidewalk and signage.
- Contact for any issues is Rob Clewley 207-717-6653.
MaineDOT regrets this inconvenience and thanks you for your patience.