MaineDOT has published the below Fact Sheet as well as "Digging Maine" - a publication of handy tips for business owners . Visit Mainedot.gov for project information.
###Downloads
- Project Fact Sheet (PDF)
- Digging Maine (PDF)
Project Facts
Construction Workdays
- Monday thru Friday. No work on Saturdays or Sundays
Times of Construction
- Mondays thru Thursdays: sunrise to sunset
- Fridays: sunrise to 3 pm
- Five 24 hours-a-day operations allowed, otherwise no night work
- No work on the following state or city holidays:
- Memorial Day- Monday, May 28th
- Independence Day- Wednesday, July 4th, 2018
- Old Hallowell Days- Friday, July 20th, 2018
- Labor Day- Monday, September 3rd, 2018
- Columbus Day- Monday, October 8th, 2018
- Veteran's Day- Monday, November 12th, 2018
Project Schedule
- Advertise the project to contractors- January 31
- Open Bids- February 21
- Contract Awarded- March 16 (or as soon as all appropriate documents have been finalized)
- Contractor to hold Open House for the public one week prior to construction launch
- Start of Construction- No later than April 2
- Finish east side of downtown- June 29
- Remove barriers and open Water Street to full width until after Old Hallowell Days (detour to remain in affect otherwise)
- Water Street downtown complete- October 5, 2018
- Construction complete (except surface pavement) November 16, 2018
- Surface Pavement- June 3 to June 6 of 2019 (Proposed to be night time operations)
- Project completed- June 6, 2019
###Downloads
- Project Fact Sheet (PDF)
- Digging Maine (PDF)
Project Facts
Construction Workdays
- Monday thru Friday. No work on Saturdays or Sundays
Times of Construction
- Mondays thru Thursdays: sunrise to sunset
- Fridays: sunrise to 3 pm
- Five 24 hours-a-day operations allowed, otherwise no night work
- No work on the following state or city holidays:
- Memorial Day- Monday, May 28th
- Independence Day- Wednesday, July 4th, 2018
- Old Hallowell Days- Friday, July 20th, 2018
- Labor Day- Monday, September 3rd, 2018
- Columbus Day- Monday, October 8th, 2018
- Veteran's Day- Monday, November 12th, 2018
Project Schedule
- Advertise the project to contractors- January 31
- Open Bids- February 21
- Contract Awarded- March 16 (or as soon as all appropriate documents have been finalized)
- Contractor to hold Open House for the public one week prior to construction launch
- Start of Construction- No later than April 2
- Finish east side of downtown- June 29
- Remove barriers and open Water Street to full width until after Old Hallowell Days (detour to remain in affect otherwise)
- Water Street downtown complete- October 5, 2018
- Construction complete (except surface pavement) November 16, 2018
- Surface Pavement- June 3 to June 6 of 2019 (Proposed to be night time operations)
- Project completed- June 6, 2019