Project Update: Week ending 04/22/2017

Having trouble viewing this email? View it as a Web page. | You are subscribed to Bar Harbor Route 3


04/18/2017 11:21 AM EDT

**All scheduling is weather dependent and subject to change. In the event that this happens, updates will be made and sent out as soon as possible.**

- The contractor will be installing water line services from Old Bar Harbor Road to Sand Point Road.

- The contractor will be removing the concrete walls near the Hulls Cove School House and working on installing water line.

- The utility companies will continue conducting telephone pole work from the Ferry Terminal towards Prospect Street, from West Street to Eagle Lake Road, and from Old Bar Harbor Road to Sand Point Road. Signal work will also be conducted at the Eagle Lake Road intersection.

- The contractor will be installing underdrain from Baymeath Road towards Sand Point Road.

- Installation for the signage for the first one way/alternate route will begin this week.