Carroll Co Roadway Projects - June 2025

View as a webpage

Maryland Department of Transportation State Highway Administration

JUNE 2025

Roadway Projects in Carroll County

All scheduled work is weather/temperature dependent

MD 27 (Manchester Road) from West of MD 140 to Hahn Road - 40% complete

  • Sections 2 and 3 are 95% complete. Upcoming work includes grading and paving.
  • Crews are test pitting at section 1 to determine the location of an underground water line. SHA will then adjust caisson placements before installation. 
  • This project will construct new bicycle/pedestrian access and connect existing sections of the Westminster Community Trail with completion expected in spring 2026. 

MD 91 (Emory Road) Bridges over the North Branch of the Patapsco River and Maryland Midland Railroad- 90% complete

  • Crews will start stormwater management work this month. The stormwater management work may require flagging operations with a single-lane restriction Monday through Friday from 9 a.m. to 3 p.m. Emergency vehicles and school buses will be given priority.
  • This project is expected to be complete in summer 2025. 

Highway Maintenance

  • These projects will remove the top layer of the roadway (milling), repair depressions and cracks, and install a new driving surface:
    • MD 27 (Ridge Rd) between Nicodemus Rd and Bond St - Crews are working on patching along with wedge and level. The next step is paving. The schedule has daytime hours.
    • MD 31 (High St) between Lambert Ave and Church St (in the town of New Windsor) will see work starting Monday, June 9. The schedule is Monday through Friday from 8 a.m. to 4 p.m. Street parking will be restricted when crews are working in that location. The roadwork is expected to be complete next month.

 

SHA Offices and Shops will close on Thursday, June 19.

 

Contact Elizabeth Harris, Community Relations Manager, for more project information: eharris8@mdot.maryland.gov