OPC urges State regulators to strengthen proposed rules for data center customers
BALTIMORE – State regulators must act quickly to strengthen proposed utility rules for Maryland data centers or Maryland households will face higher electricity bills and potential outages caused by data centers, the Office of People’s Counsel said in comments filed with the Public Service Commission (PSC) Friday.
The major Maryland utilities recently filed proposals with the PSC to address the rules for hyperscale data centers wanting to locate in Maryland, called “large-load tariffs.” The filings fail to fully address data center cost allocation and reliability risks for residential customers as recent Maryland legislation requires, OPC’s comments explained.
“The General Assembly has made clear that residential utility customers should not bear the costs associated with new data center load growth,” People’s Counsel David S. Lapp said. “It’s up to the PSC to require changes to the Maryland utilities’ proposals so that customers are fully protected from data center-driven costs.”
OPC’s comments emphasize the PSC’s clear legal authority to set retail service rules without encroaching on federal jurisdiction and warned that any delay risks allowing incoming large-load customer (primarily hyperscale data center) projects to be “grandfathered” and avoid the protections the General Assembly intended for existing customers.
Customer-specific charges, a calculated surcharge mechanism, a “bring-your-own-generation” requirement, or the right combination of these solutions, are necessary to protect residential customers from cost increases due to new Maryland hyperscale data centers, OPC’s comments pointed out, explaining that utility tariffs initially should address:
- The costs utilities spend on studies for integrating new data centers with the electric system, which should be charged directly to the data center and paid up front;
- The costs of distribution upgrades and for local transmission projects that are required to serve the data center customer, which should be collected up front or through customer-specific charges;
- Regional transmission and, importantly, energy costs, for which the tariffs should require the utility to (1) retain a consultant, paid for by the data center, that is charged with identifying the customer’s impact on Maryland transmission costs, and (2) refund to other customers any costs they pay as a result of higher transmission rates and energy prices attributable to the data center customer;
- Increases in capacity prices caused by the data center, which would be best addressed by a “bring-your-own-new-capacity” requirement, with additional provisions to mitigate any remaining capacity market or reliability backstop auction cost impacts; and
- Potentially stranded capacity or transmission costs caused by the data center customer’s forecasted needs if those needs are delayed, reduced, or never materialize, which costs are best addressed by the data center’s posting of collateral before costs are incurred.
OPC’s comments also point out that the tariff rules should address data center “curtailment”—when data centers should eliminate or reduce their use of the power system—to protect existing customers from reliability risks that the data centers pose. Specifically, the PSC should require that each utility tariff subject data centers to mandatory curtailment during defined pre-emergency and emergency conditions.
The PSC also should initiate a separate proceeding to examine utility policies for addressing directives from PJM to curtail service, including designation of “critical loads,” such as hospitals, and service interruption priority that protects residential customers, OPC explained.
The major Exelon utilities (BGE, Pepco, and Delmarva Power), Potomac Edison, and Southern Maryland Electric Cooperative each filed their proposed tariffs in September. OPC’s filing includes a table that compares OPC’s, Staff’s, and each utility’s proposal on key features of an effective large-load tariff.
“The PSC needs to act expeditiously because Maryland utilities are making consequential decisions in response to data center requests for service, including developing construction plans, entering service arrangements, planning investment, and, in some cases, beginning construction,” Lapp said.
OPC filed its comments as part of the PSC’s ongoing large-load tariff proceeding, required under the 2025 Next Generation Energy Act and enhanced by the 2026 Utility RELIEF Act and ahead of upcoming legislative-style hearings where the PSC will review specific utility tariff proposals.
Visit OPC’s website to learn more about the costs and risks caused by data centers and OPC’s advocacy to protect residential customers.
The Maryland Office of People’s Counsel is an independent state agency that represents Maryland’s residential consumers in electric, natural gas, telecommunications, private water and certain transportation matters before the Public Service Commission, federal regulatory agencies, and the courts.
* * *
|