Spring Construction Underway for Montgomery County’s Annual Sidewalk Programs
Montgomery County Maryland sent this bulletin at 04/23/2026 02:07 PM EDTFor Immediate Release: Thursday, April 23, 2026
Spring Construction Underway for Montgomery County's Annual Sidewalk Programs

The Montgomery County Department of Transportation (MCDOT) is rolling out its spring sidewalk construction schedule, with approximately 10 miles of new sidewalks in the active planning or construction phase across the County.
MCDOT currently has 30 sidewalk projects, totaling six miles of new walkways, in the active planning or construction phase under the Annual Sidewalk Program. An additional four sidewalk projects, totaling 1.3 miles, are in progress and will be combined with additional pedestrian safety improvements such as crosswalks and signage under the Safe Routes to School (SRTS) program. Construction has already been completed on a sidewalk near Travilah Elementary School as part of SRTS.
The County is also proposing 2.7 miles of new sidewalk to connect residents to the upcoming Purple Line light rail, which is scheduled to open in winter 2027, under the Purple Line Bicycle and Pedestrian Priority Areas (BiPPA) program.
These projects represent an investment of nearly $10 million in pedestrian safety and mobility.
“MCDOT’s work to build safer pedestrian pathways is making a meaningful difference in our community,” said Montgomery County Executive Marc Elrich. “Safe sidewalks provide critical connections to jobs, public transportation, schools, and other vital services. As we look to modernize and upgrade our infrastructure, we are focusing on efforts that improve mobility without contributing to traffic congestion.”
The Annual Sidewalk Program addresses critical gaps in the County’s sidewalk network to improve connectivity, enhance safety, and promote alternative modes of transportation. MCDOT maintains nearly 1,700 miles of sidewalks across the County.
MCDOT conducts safety assessments at fifteen to twenty public schools each year, as part of SRTS, to recommend improvements within the school walkshed to provide safe and accessible routes for students walking and biking to school.
“We receive between 250-300 requests for new sidewalks each year,” said MCDOT Director Chris Conklin. “We evaluate each request within a week of receiving it and rate the proposed location using objective criteria that includes assessment of risks to pedestrian safety, critical connections to vital services such as community resources and public transportation, and locations in historically underrepresented neighborhoods where residents are least able to afford private transportation. Once a project is selected for potential sidewalk construction, community meetings let us gather feedback that guide our implementation plans. The goal is to create safe, accessible passageways that are inclusive of the needs of our communities.”
MCDOT collects community input, in part, to determine whether a public hearing is legally required. If a proposed sidewalk has broad community support, the project can advance without a hearing.
For sidewalk proposals with a high priority rating, public hearings and the community feedback collected allow MCDOT to make adjustments in the project design to incorporate special requests for sidewalk alignment, tree preservation, minor drainage modifications, and materials selection.
For projects with lower objective criteria ratings, community sentiment can have a greater influence on whether to advance or defer individual projects. Residents can find more information about how sidewalk projects are implemented on the Sidewalk Program FAQ page.
Under the Annual Sidewalk Program, MCDOT assigns a priority rating to each requested sidewalk, focusing on the following factors:
- Safety (50%) – Pedestrian level of comfort and crash history.
- Trip Generators (30%) – Schools, shopping centers, community and recreation centers, parks, pools, library, bus and Metro Transit stops.
- Equity Emphasis Area (20%) – Assessment of whether the requested sidewalk is in an equity emphasis area.
Preliminary lists of current or scheduled sidewalk construction projects and current or scheduled SRTS projects are available online. Both sites will be updated throughout the spring and summer as projects are added to the schedule.
Projects included in the Annual Sidewalk Program's preliminary schedule:
Silver Spring
- Bradford Road (planning phase)
Priority Rating: 90/100
MCDOT has proposed .09 miles (482 linear feet) of five-foot-wide concrete sidewalk to be constructed on the east side of Bradford Road from Hartwell Road to Plymouth Street.
The public is encouraged to visit the project website and provide feedback by email to Planning Specialist Lori Main at Lori.Main@montgomerycountymd.gov by 5 p.m. Friday, April 24.
- Caroline Avenue (planning phase)
Priority Rating: 95/100
MCDOT has proposed 0.18 miles (938 linear feet) of five-foot-wide concrete sidewalk to be constructed along Caroline Avenue from Franklin Avenue to Leighton Avenue.
The public is encouraged to visit the project website and provide feedback by email to Planning Specialist Lori Main at Lori.Main@montgomerycountymd.gov by 5 p.m. Monday, May 11.
- Hartwell Road (planning phase)
Priority Rating: 95/100
MCDOT has proposed 0.04 miles (240 linear feet) of five-foot-wide concrete sidewalk to be constructed on the north side of Hartwell Road from Reading Road to Bradford Road.
The public is encouraged to visit the project website and provide feedback by email to Planning Specialist Lori Main at Lori.Main@montgomerycountymd.gov by 5 p.m. Friday, April 24.
- Rippling Brook Drive (construction phase)
Priority Rating: 94.5/100
Approximately 0.26 miles (1,406 linear feet) of five-foot-wide concrete sidewalk will be constructed on the east side (odd-numbered properties) of Rippling Brook Drive from Bel Pre Road to the existing sidewalks.
The sidewalk projects currently in the construction phase under SRTS include:
Potomac
- Cabin John Middle School
Approximately 0.45 miles (2,400 linear feet) of five-foot-wide concrete sidewalk is being constructed along Bells Mill Road, from Gainsborough Road to Fox Hills Trail. Existing ramps will be rebuilt to be ADA-compliant, and high-visibility crosswalks will be installed.
Germantown
- Martin Luther King Middle School
A total of approximately 0.5 miles (2,700 linear feet) of five-foot-wide concrete sidewalk is being constructed around Martin Luther King Jr. Middle School, Lake Seneca Elementary School, and Waters Landing Elementary School walksheds in the following locations:
- Wanegarden Drive: Between Lake Seneca Elementary School and Wynnfield Drive
- Waldorf Drive: Between Wisteria Drive and Wynnfield Drive (east side of roadway only)
- Teakwood Lane: Between Willow Cove Manor driveway entrances, connecting gaps between existing sidewalks
- Northwood High School
Approximately 0.13 miles (700 linear feet) of five-foot-wide concrete sidewalk is being constructed along Gabel Street from Breewood Road to University Boulevard.
- Roscoe Nix Elementary School
Approximately 0.22 miles (1,160 linear feet) of five-foot-wide concrete sidewalk is being constructed along Mount Pisgah Road from Oakview Drive to Grey Castle Way.
During the previous fiscal year, which ran from July 1, 2024, to June 30, 2025, MCODT constructed 5.85 miles of sidewalk, including 1.5 miles around schools under the County’s Safe Routes to Schools program.
Residents who wish to request a sidewalk or check the status of a current request can do so via MCDOT’s online sidewalk request portal or by calling MC311. MC311 can be reached by dialing 311 within the County or 240-777-0311 from anywhere, 7 a.m. to 7 p.m., Monday through Friday.
For information on MCDOT programs and services visit montgomerycountymd.gov/department-transportation, follow @MCDOTNow on X, Bluesky, Facebook, Instagram and subscribe to MCDOT’s “Go Montgomery!” newsletter.
# # #
Media Contact: Emily DeTitta, 240-372-2282