Today, the Maryland Transportation Authority (MDTA) Board approved a $38.6 million Demolition and Miscellaneous Marine Work contract, in support of the Key Bridge Rebuild Project. The contract was awarded to Joseph B. Fay Company, marking another important step in the reconstruction of the Francis Scott Key Bridge. Additionally, the MDTA today launched a new online interactive tool at KeyBridgeRebuild.com that gives Marylanders an up-close view of the replacement bridge’s three sections and details and photos of the various elements. Find the latest project updates at the Key Bridge Rebuild Progress Dashboard.
“The Moore-Miller Administration has promised to work expeditiously to rebuild the Key Bridge, and the speed with which the MDTA moved to award this contract is a testament to our commitment,” said Maryland Department of Transportation Secretary and MDTA Board Chair Katie Thomson. “Work is actively taking place on the Key Bridge Rebuild, as residents and businesses have observed. The demolition and marine work associated with the newly awarded contract is expected to begin later this fall and MDTA is advancing three other procurements while construction is underway.”
The MDTA invited contractors to submit proposals for the Demolition and Miscellaneous Marine Work contract in August. Bids were received at the end of October and evaluated by the MDTA Division of Procurement, and the contract was awarded to the lowest-priced, qualified bidder.
“This contract award represents another step forward in our commitment to rebuilding the Key Bridge as quickly, safely and cost-effectively as possible,” said MDTA Executive Director Bruce Gartner. “We've continued making progress on construction while advancing the demolition contract and other procurements in parallel. Removing the remaining structures over the water is an important part of that coordinated effort as we move closer to delivering the new bridge.”
The contract is one of four planned procurements to complete the Key Bridge Rebuild and focuses on removing the remaining portions of the former bridge over the Patapsco River, along with other marine activities necessary to support ongoing construction of the new bridge.
The Demolition and Miscellaneous Marine Work contract includes:
-
Removal and salvage of steel girder spans: Removing the remaining three-span steel girder sections over the Patapsco River, near each riverbank.
-
Demolition of marine piers: Demolishing eight existing marine piers that supported the former bridge.
-
Demolition of land piers: Completely removing two remaining land piers, one on each side of the river.
-
Underwater demolition: Removing nine marine foundations to the mud line of the river.
-
Steel pipe pile clean-out: Cleaning out 96-inch-diameter steel pipe piles to make way to pour concrete for the new bridge.
The contract builds on demolition work completed in February when crews finished mechanically removing the land-based portions of the former Key Bridge. That work included removing more than 20,000 tons of concrete decking and columns, along with steel girders on the north and south sides of the bridge.
Joseph B. Fay Company, which operates as part of S&B USA Construction, is a mid-Atlantic infrastructure company with local ties. They recently served as part of a joint venture with Skanska on the CSX’s Howard Street Tunnel Project in Baltimore City.
Construction of the new Key Bridge continues while MDTA advances the remaining procurements. Crews are installing permanent foundation and pier protection piles and have finished constructing the temporary over-water work platforms, known as trestles, to support construction of the new bridge.
In May, MDTA announced plans to deliver the remaining rebuild work through four separate contracts:
- Demolition and Miscellaneous Marine Work
-
South Land Approach
Advertise in late fall 2026/early winter 2027, begin construction in spring 2027
-
North Land Approach
Advertise in winter 2027, begin construction in late spring 2027
-
Main Span and Marine Approaches
Advertised July 21, begin construction in summer 2027
This process is intended to increase competition, expand opportunities for the local workforce and expedite the award of new contracts.
The MDTA continues to work toward its goal of opening the new Key Bridge to traffic by 2030. The construction schedule will be further refined as the remaining contracts are awarded and contractor schedules are established.
The MDTA’s new online interactive tool provides users with a detailed view of the Key Bridge Rebuild’s three sections: the south land approach, north land approach and main span and marine approaches.
Users can click on these different sections to see details and photos of various elements, including the typical sections, cable-stayed bridge and foundations, pylons and foundations, pier protection systems and approach spans.
Visit KeyBridgeRebuild.com to view the new interactive tool and the recently announced progress dashboard.
 The MDTA finances, owns, operates, secures and maintains Maryland’s toll bridges, tunnels and turnpikes. The MDTA is self-sufficient and receives no gas tax, motor vehicle fees or other revenue from the state’s Transportation Trust Fund, and the MDTA's projects and services are funded through tolls paid by the customers who use their facilities.
|