2024 CBD Right of Way Project
Scope: Roadway resurfacing, re-striping, sidewalk repairs, installation of Americans with Disabilities Act (ADA)-compliant ramps, and driveway apron repairs
Locations:
- Old Poydras St (S. Broad - S. Galvez)
- Old Poydras St. (S. Galvez – Dead End)
- Perdido St. (S. Galvez St. – Claiborne Ave.)
- Perdido St. (Loyola Ave. – St. Charles Ave.)
- Gravier St. (LaSalle St. – Loyola Ave.)
- Union St. (S. Rampart St. – Carondelet St.)
- Natchez St. (Camp St – Tchoupitoulas St.)
- Maestri Pl. (St. Charles Ave. – Camp St.)
- Maestri Pl. (St. Charles Ave. – Camp St.)
- Girod St. (Loyola Ave. – Convention Center Blvd.)
- Howard Ave. (Loyola Ave. – Tivoli Circle)
- Prieur St. (Perdido St. – Tulane Ave.)
- Carondelet St. (Poydras St. – Canal St.)
- St. Charles Ave. (Poydras St. – Canal St.)
- Broad St. (Howard Ave.- Euphrosine St.)
- Johnson St. (Perdido St. – Tulane Ave.)
- Rampart St. (Canal St. – Tulane Ave.)
- Gaiennie St. (S. Peters St. – Convention Center Blvd.)
- John Churchill Chase St. (Annunciation St. – Dead End at Calliope St.)
- Poeyfarre St. (Annunciation St. – Magazine St.)
- Constance St. (John Churchill Chase St. – Andrew Higgins Blvd.)
Status: Paving operations are currently underway on Rampart and Dryades, with striping scheduled next week. Crews will also complete minor striping tasks, including triangles and corner zones, on Perdido and Girod.
2024 FQ Right of Way Project
Scope: Roadway resurfacing, re-striping, sidewalk repairs, installation of Americans with Disabilities Act (ADA)-compliant ramps, and driveway apron repairs
Locations:
- Gov. Nicholls Street: 600 – 1000 blocks
- Ursulines Avenue: 500 – 1000 blocks
- St. Philip Street: 600 – 1000 blocks
- St. Ann Street: 600, 900 – 1000 blocks
- St. Louis Street: 1100 block
- Madison Street: 600 block
- St. Peter Street: 700-1000 block
- Conti Street: 500 – 600 / 900 – 1100 blocks
- Clinton Street: 200 block
- Chartres Street: 100 – 600 / 800 – 1300 blocks
- Frenchmen Street: 400 – 600 blocks
- Burgundy Street: 2200 – 2500 blocks
- Decatur Street: 2200 – 2500 blocks
Status: Crews are scheduled to resume work on Iberville St. between Royal and Chartres on Tuesday, March 11. They will be removing concrete roadway panels and resurfacing the roadway with asphalt pavement.
 |
|
2024 CBD Right of Way - Phase 2 Improvements
Scope: Patch, Mill and Resurfacing work at various locations
Locations: Magazine Street (Nashville Avenue to East Drive)
Status: Resurfacing on Magazine St. from Nashville Ave. to East Dr. has been completed.
Excavation work at Monument Plaza located at Basin and Canal is ongoing.
|
Hotel Collapse Site Rehabilitation
Scope: Waterline installation, drainage upgrades, pavement, and sidewalk restoration
Status: RTA grout repairs at the Canal and Rampart intersection resumed this week and will continue for the next few weeks.
Downman Road / Lincoln Beach Project
Scope: Road resurfacing, striping, sidewalk repairs, and underground utility updates
Locations:
-
Downman Road: Chef Menteur Hwy to Seabrook Bridge
-
Lincoln Beach Blvd: Press Dr to France Rd
-
Providence Place: Press Dr to New York St
-
Leon C. Simon: Press Dr to Elysian Fields Ave
Status: On Leon C. Simon, crews continue to remove and replace concrete roadway panels from Elysian Fields to the Seabrook Bridge. One lane of traffic will remain open in the direction where construction is not taking place.
|
Scope: Repairing and upgrading concrete and specialty sidewalks (brick/stone)
Status:
-
Barracks Street (Rampart – Decatur): All work is complete except in the 700 block, where a water leak must be repaired by the Sewerage & Water Board before construction can resume.
Please Help Us Get the Message Out
We want to ensure our updates reach as many people as possible, including Central Business District and French Quarter businesses, residents, hospitality workers, and more.
Please help us get the message out by sharing our weekly updates with your neighbors and staff. Feel free to post this information in your breakrooms or common areas.
If you know anyone or any group that would like to be added to our distribution list, please sign up here.
Stay Informed
To stay informed about street closures related to these repairs, sign up for the Department of Public Works Road Construction Alerts. Receive direct updates from the City of New Orleans on city-related road construction, including traffic notifications, road closures, and other impacts. Thank you for your patience and cooperation as we improve the streets of New Orleans.
Department of Public Works City of New Orleans 1300 Perdido Street | 6W03 New Orleans, LA 70112
|