Interstate 165 Interchange Ramp Closures Scheduled in Butler County Next Week

BOWLING GREEN, Ky. (Aug. 29, 2024) The ongoing rehabilitation and resurfacing project on I-165 in Butler County is expected to create ramp closures beginning next week.

The schedule for the ramp closures is listed below. All work is subject to change and is weather-dependent.

Thursday, Sept. 5

  • Exit 26 northbound on-ramp – The ramp will close at 6 a.m. and reopen later that night. The detour will use U.S. 231, KY 1468 and KY 70.

Friday, Sept. 6

  • Exit 26 southbound off-ramp - The ramp will close at 6 a.m. and reopen later that night. The detour will use Exit 27, KY 70, KY 1468 and U.S. 231.

Monday, Sept. 9

  • Exit 27 northbound on-ramp - The ramp will close at 6 a.m. and reopen later that night. The detour will use I-165 southbound to Exit 26 and re-enter I-165 northbound at Exit 26.

Tuesday, Sept. 10

  • Exit 27 southbound on-ramp - The ramp will close at 6 a.m. and reopen later that night. The detour will use KY 70, KY 1468 and U.S. 231.

Thursday, Sept. 11

  • Exit 27 northbound off-ramp - The ramp will close at 6 a.m. and reopen later that night. The detour will use Exit 26, U.S. 231, KY 1468 and KY 70.

Friday, Sept. 12

  • Exit 27 southbound off-ramp - The ramp will close at 6 a.m. and reopen late that night. The detour will use I-165 southbound to Exit 26 and re-enter I-165 northbound at Exit 26.

The entire project is expected to be completed by November 1.

 

###