Weekend closure scheduled for I-264 East to support paving operations; overnight I-71 ramp closures planned for bridge work
LOUISVILLE, Ky. (Aug. 11, 2026) – As work continues to progress on the $130 million widening and improvement project of Interstate 264 (Watterson Expressway) and U.S. 42 (Brownsboro Road) in Louisville, the Kentucky Transportation Cabinet (KYTC) advises motorists of the upcoming weekend closure of I-264 East and an updated schedule for the overnight ramp closures on I-71.
Beginning at 8 p.m. on Friday, Aug. 14, through 6 a.m. on Monday, Aug. 17, I-264 East will be closed at the I-64/I-264 split at mile marker 18 to mile marker 22 (near U.S.42/Brownsboro Road). Traffic will still be able to enter I-264 East from U.S. 42 to reach I-71 North and South. Motorists should plan to detour by taking I-64 East to I-265 North to I-71 South to continue on I-71 South or I-264 West to reach destinations within the closure area.
The weekend closure of I-264 East is to allow contract crews to complete asphalt paving operations necessary for upcoming traffic shifts. As work progresses, traffic will be moved from the outside lanes to the inside lanes following the weekend closure. Additionally, overnight ramp closures on I-71 to allow contract crews to place girders on the I-71 South ramp bridge over the Watterson Expressway (I-264) interchange ramps have been rescheduled.
The following traffic restrictions will be in place nightly from 8 p.m. to 6 a.m. on Thursday, Aug. 27, and Friday, Aug. 28:
- The I-264 East ramp to I-71 South will be closed (Exit 23B) – motorists should take I-71 North to I-265 North to reach I-71 South.
The following traffic restrictions will be in place nightly from 8 p.m. to 6 a.m. beginning Monday, Aug. 31, through Wednesday, Sept. 2:
- The I-264 East ramp to I-71 South will be closed (Exit 23B) – motorists should take I-71 North to I-265 North to reach I-71 South.
- The I-71 South ramp to I-264 West will be closed (Exit 5) – motorists should continue on I-71 South to Zorn Avenue at Exit 2 to I-71 North to reach I-264 West.
- I-71 North will be closed at mile point 4.9 – motorists will be able to continue to I-264 West at Exit 5 and should detour to either U.S. 42 (Brownsboro Road) at Exit 22 or KY 1447 (Westport Road) at Exit 21 to connect with I-264 East to proceed on to I-71 North.
The I-71 North ramp to I-264 West will remain open at Exit 5. The I-264 East ramp to I-71 North will also remain open (Exit 23A).
The interstate project is expected to be completed by the Fall of 2027. The work is being carried out by Cleary Construction Inc. of Monroe County, Kentucky. More details, including project timelines and traffic impacts, will be shared online as work progresses. Motorists are encouraged to sign up for email and text alerts regarding weekly traffic impacts pertaining to the project.
The date and duration of this work may be adjusted if inclement weather or other unforeseen delays occur. For the latest traffic and travel updates across the Commonwealth of Kentucky, visit goky.ky.gov. Information specific to District 5 counties is also available on Facebook and X.
LOUISVILLE, Ky. (Aug. 13, 2026) – The Kentucky Transportation Cabinet (KYTC) advises motorists of an upcoming lane closure on Interstate 71 North on Monday, Aug. 17, in Oldham County.
The right lane of I-71 North from mile marker 18 (near KY 393) to mile marker 22 (near KY 53) will be closed from 9 a.m. to 9 p.m. on Monday, Aug. 17. The lane closure is necessary for KYTC crews to perform routine maintenance of the interstate. Motorists should heed signage and use caution when traveling through the work zone.
 Tonight the Metro Council voted in favor of a six-month moratorium on permits allowing for zoning changes or any new construction of large-scale data centers within Louisville Metro. The Ordinance (O-135-26) gives Metro the time to conclude our work on land development code regulations for the review of zoning changes related to the construction of large-scale data centers. The public meetings for these policies have just concluded and planning staff will work with members of the planning commission to complete their final recommendations for new regulations. Once these have been passed by the commission, the Metro Council will have the opportunity to review them, and take a final vote.
Should any delays occur that would prevent action prior to the conclusion of the six-month moratorium, the Metro Council would have the ability to extend the moratorium. This fact helps to assure people that nothing will be able to slip through the cracks. All new large-scale data centers will be subject to these new regulations that take into consideration extensive public input.
We do plan on ensuring that the regulations address the serious concerns of our constituents. They include protections for air and water quality, and not transferring energy or water use costs to residential customers.
Data Centers aren’t new to our region, but the construction of large-scale data centers are. I am hopeful that our work over the past year, as well as the work undertaken by the planning commission, will help us chart a long-term plan for addressing these types of proposals.
I-65 has partially reopened.
It’s important to remember I-65 will remain a construction zone, open to two lanes of traffic in each direction with a reduced speed limit of 40 mph for much of the corridor from the Watterson (I-264) to downtown (Jefferson Street). There will be a section of southbound I-65 south of the Hill/CSX/Burnett bridge that will be 45 mph. We will continue to urge through traffic to use the signed detour and swing to the west with I-264 (Georgia Davis Powers Expressway) to avoid construction. And we will continue to urge drivers to use mapping apps for the best routes at their time of travel.
Work on these three critical bridges will continue through March 2027. The approach is being finalized to rehabilitate or replace six additional bridges. The end date for the project will be known when that approach is finalized.
I65CentralCorridor.com
The Louisville Metro Police Department is asking residents to take a few simple steps to help prevent vehicle thefts and break-ins as the city continues to see an increase in these crimes.
Remember: Lock, Take, Hide.
-
Lock your car every time you leave it unattended.
-
Take your keys and firearms with you. Never leave them inside your vehicle.
-
Hide your belongings or remove valuables from plain sight.
These simple precautions can significantly reduce the risk of becoming a victim of theft.
LMPD is actively working to address these crimes and recently arrested several individuals connected to vehicle break-ins as part of an ongoing effort to target offenders. However, prevention and public awareness remain important tools in keeping our neighborhoods safe.
If you observe suspicious activity, please contact LMPD's non-emergency line at (502) 574-7111.
Together, we can help make Louisville a safer and stronger community.
|
|
|
|
The Louisville Sports Commission, in partnership with Swags Sport Shoes and UofL Health, will host the kickoff event for the 2026 Urban Bourbon Half Marathon and Urban Bourbon 5K training program.
Whether training for the half marathon, 5K or simply looking to improve their fitness, runners of all experience levels are encouraged to attend.
Attendees will be able to:
· Register for the Urban Bourbon Half Marathon or Urban Bourbon 5K at a discounted rate.
· Pick up a free race training plan.
· Meet the official race pacers and learn about the weekly Swags group training runs leading up to race day.
· Speak with Swags experts about proper footwear and training tips.
· Enter to win a Swags Fitted Experience—including one pair of shoes, insoles and socks—by checking in on the Swags app.
Representatives from the following organizations will also be available:
· UofL Health – Sports Medicine
· UofL Health – Frazier Sports
· UofL Health – Emergency Medicine/Events Management
NOTE: At 7 p.m., participants are invited to join a short, organized run along Southern Parkway and demo the new Diadora Corsa running shoe.
|
|
|
|
|
|
Tuesday, August 11, 2026
5 – 7 p.m.
|
|
|
|
|
|
Swags Sport Shoes
323 W. Woodlawn Avenue
Louisville, Ky. 40214
|
|
|
###
ABOUT Louisville Sports Commission
The Louisville Sports Commission (LSC) is a Louisville, Kentucky-based 501(c)(3) organization whose mission is to create a legacy of economic and social vitality through sports. The LSC attracts and hosts sporting events and activities that have a positive economic impact on Louisville, enhance the area's image as a premier sports destination, and promote active lifestyles to help improve the quality of life for community members of all ages. More information is available online at www.louisvillesports.org, www.facebook.com/louisvillesportscommission and @SportsinLou.
ABOUT Swags Sport Shoes
Founded in 1980, Swags is Kentuckiana’s trusted community running store, dedicated to helping athletes and everyday movers find the right fit through expert footwear and apparel fitting. Owned and operated by sisters Allie and Layney Vincent, Swags has grown into a hub for running, walking, and lifestyle footwear with three retail locations and a mobile Pop-Up Store. Building on more than four decades of tradition, Swags continues to serve Kentuckiana with expertise, innovation, and a strong community spirit.
ABOUT UofL Health
UofL Health is a not-for-profit (501(c)(3)) fully integrated regional academic health system with nine hospitals, four medical centers, Brown Cancer Center, Eye Institute, more than 250 physician practice locations, and more than 1,200 providers in Louisville and the surrounding counties, including southern Indiana. Additional access to UofL Health is provided through a partnership with Carroll County Memorial Hospital.
Affiliated with the University of Louisville School of Medicine, UofL Health is committed to providing patients with access to the most advanced care available. This includes clinical trials, collaboration on research and the development of new technologies to both save and improve lives. With more than 14,000 team members – physicians, surgeons, nurses, pharmacists and other highly-skilled health care professionals, UofL Health is focused on one mission: to transform the health of communities we serve through compassionate, innovative, patient-centered care. For more information on UofL Health, go to www.UofLHealth.org.
|
|
Join the Jefferson County Soil & Water Conservation District at Blackacre Community Gardens for a free Cover Crop Workshop and Giveaway. Discover how cover crops can enrich soil, reduce erosion, suppress weeds, and prepare your garden for a successful growing season.
- Saturday, September 26
- 10:30 - 11:30 a.m.
- Blackacre Community Gardens, 3200 Tucker Station Road, Louisville, KY 40299
Free cover crop seeds will be available for Jefferson County residents, and the workshop will cover how and when to use them in your garden beds. Reserve your seeds today at tinyurl.com/SWCDCover
New items or changes in project status are shown in bold
Inclement weather or other unforeseen circumstances may arise, and as such, the information provided below is for advisory purposes only and subject to change without prior notice.
Pothole patching, sweeping, drain & ditch cleaning, striping, pavement marking, and maintenance crews may work on major interstates during non-peak daytime hours and at night. Motorists should watch for roadside maintenance on interstates and highways daily throughout the district.
| Jefferson County |
|
I-65 Central Corridor
 |
I-65 is open to two lanes of traffic in each direction between the Watterson (I-264) and downtown Louisville (Jefferson Street).
Additional information related to the I-65 Central Corridor project can be found online at i65centralcorridor.com.
|
U.S. 31E (Main Street) *Main Remade* |
TRAFFIC ADVISORY: By the end of the day on Thursday, July 30, Main Street between Wenzel Street and Second Street will be converted to its new two-way traffic configuration.
As part of this transition, most signalized intersections along the corridor will temporarily operate as all-way stops using stop signs while crews complete the activation of the new traffic signals. The intersection of Main Street and Second Street will remain signalized during this phase.
The temporary all-way stop conditions will remain in place until the new traffic signals are fully activated. Additional information will be shared once the signal activation process is complete.
Temporary signs will be installed throughout the corridor to alert motorists of the new traffic pattern and stop-controlled intersections. Drivers should pay close attention to posted signage, obey all stop signs and other temporary traffic control devices, and use extra caution while traveling through the area.
|
| U.S. 60 (Shelbyville Road) |
Traffic Impacts: Daily lane closures are possible. Date/Time: Daily. Project Limits: U.S. 60 (Shelbyville Road) between KY 2861 (Eastwood Cutoff Road) and Rockcrest Way. Type of work: Widening and improvement project. Other Details: Please visit the project webpage for additional information.
|
| I-64 East and West |
Traffic Impacts: Lane and shoulder closures are possible. Date/Time: Daily/nightly. Project Limits: I-64 East and West from Second Street in downtown Louisville to the I-64/I-264 interchange near the Sherman Minton Bridge in west Louisville. Type of Work: Preventative maintenance project. |
| I-64 East and West |
Traffic Impacts: Lane closures are possible as final items as part of the project are underway. Date/Time: Daily/nightly. Project Limits: I-64 East and West at mile point 11.799, near Exit 10 (Cannons Lane) on I-64 West, and near Exit 12 to I-264 (Watterson Expressway) on I-64 East. Type of Work: Bridge replacement project. Other Details: *Project announcement press release
|
| I-65 South (John F. Kennedy Memorial Bridge) |
As work on the final phase of the expansion joint replacement project on the John F. Kennedy Memorial Bridge nears completion, contract crews will implement lane closures on Interstate 65 South beginning Saturday, Aug. 15, to complete striping operations. The project will preserve and extend the service life of this critical Ohio River crossing. Beginning Saturday, Aug. 15, at 12 p.m., through Sunday, Aug. 16, at 6 p.m.
- The right three lanes of the Kennedy Bridge will be closed.
- The I-65 South to I-64 West ramp remains closed and will reopen on Sunday, Aug. 16, at 6 p.m.
Contract crews will use this weekend's lane closures to complete final striping operations and to apply interstate shields to the lanes, helping motorists better identify lane movements. Motorists should heed signage, use caution, and plan for additional travel time.
|
| I-71 Widening and Improvement Project |
**Traffic impacts available here.**
|
| U.S. 150 (East Broadway) |
*Signal and median installations are underway and lane closures are possible on the east side of Barrett Avenue at Broadway and on Broadway between 9th Street and Barrett Avenue from 9 a.m. to 3p.m. daily.
Paving operations are expected to begin in August and will continue through early September.*
Traffic Impacts: Lane closures are possible. Date/Time: Daily/nightly. Project Limits: U.S. 150 (East Broadway) between South 9th Street and Baxter Avenue. Type of Work: Highway safety improvement project. |
| I-264/U.S. 42 (Brownsboro Road) Improvement Project |
**Traffic impacts available here.**
|
| KY 864 (Logan Street/Shelby Street) |
*Paving is expected to begin mid-August, and the reconfiguration is expected to be completed by mid-September. *
Traffic Impacts: Sidewalk and lane closures are possible. Date/Time: Daily and nightly. Project Limits: Between Goss Avenue and East Gray Street. Type of Work: One-way to two-way conversion of the roadway. Other Details: Link - Project Webpage
|
| KY 1819 (Billtown Road) |
*The KY 1819 (Billtown Road) project is substantially complete with final items remaining. Lane closures and delays are possible while final items are underway.*
Traffic Impacts: Lane closures and delays are possible. Date/Time: Daily – 9 a.m. to 4 p.m. Project Limits: Three sections of KY 1819 (Billtown Road):
- Easum Road through Mary Dell Lane
- Michael Edward Drive through Fairground Road
- Shady Acres Lane through Colonnades Place
Type of Work: Reconstruction of KY 1819 (Billtown Road) from North of Colonnades Place to south of Easum Road with new traffic signals, signal optimization, turn lanes, storage lanes, etc. (varying by intersection based on existing conditions and future traffic projections). Other Details: The reconstruction project is substantially complete with final punchlist items remaining. *Project webpage
|
| KY 1932 (Chenoweth Lane) |
Traffic Impacts: Lane closures and delays are possible. Date/Time: Daily from 9 a.m. to 3 p.m. Project Limits: KY 1932 (Chenoweth Lane) between U.S. 60 (Shelbyville Road) and U.S. 42 (Brownsboro Road). Type of Work: Construction activities include roadway modifications, sidewalk and pedestrian crossing improvements, and drainage enhancements designed to reduce flooding and improve overall travel conditions in the area. Other Details: This project is expected to be completed by the Fall of 2026. Motorists will be directed through the work zone via flagging operations. Drivers should heed flagging operations and use caution when traveling through the work zone. |
| KY 2054 (Algonquin Parkway) |
Traffic Impacts: Lane closures and delays are possible. Date/Time: Daily/nightly. Project Limits: KY 2054 (Algonquin Pkwy) between 40th Street (mile point 0.0) and Winkler Avenue (mile point 3.3). Type of Work: Resurfacing and improvement project. Other Details: KY 2054 (Algonquin Pkwy) between 40th Street (mile point 0.0) and Winkler Avenue (mile point 3.3) is currently four travel lanes. The reconfiguration project consists of converting the roadway to two travel lanes with the addition of a two-way left-turn lane (TWLTL). Additional improvements include installing new signage & pavement markings, rebuilding traffic signals, and constructing concrete sidewalk ramps & median modifications. The project is expected to be completed by the Fall of 2026. |
| *Various Locations |
Traffic Impacts: Lane closures and delays are possible as part of a mobile operation. Date/Time: Daily – 8 p.m. to 5 a.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone. |
| *Various locations along I-265/KY 841 (Gene Snyder Freeway) |
Traffic Impacts: Shoulder closures are possible. Project Limits: KY 841 and I-265 within Jefferson County. Date/Time: Daily/nightly. Type of Work: Staking poles for bases of new signage. |
| |
|
| Bullitt County |
|
| KY 245 (Clermont Road) |
Traffic Impacts: Daily lane closures are possible. Date/Time: Daily. Project Limits: KY 245 (Clermont Road) between the I-65 interchange and Happy Hollow Road. Type of Work: Widening and improvement project. Other Details: Please visit the project webpage for additional information.
|
| KY 1526 (Brooks Hill Road) |
Traffic Impacts: Lane closure. Date/Time: Beginning Monday, July 20, through Tuesday, Aug. 4. Project Limits: KY 1526 (Brooks Hill Road) between Holsclaw Hill Road and Brook View Road. Type of Work: Slope stabilization on the hill at mile point 9.68. Other Details: Motorists will be directed through the work zone via automated flagger assistance devices. Drivers should heed the automated flagger assistance devices, reduce speeds, and use caution when traveling through the work zone. |
| *Various Locations |
Traffic Impacts: Lane closures and delays possible as part of a mobile operation. Date/Time: Daily – 7 a.m. to 9 p.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone. |
| *Various Locations on I-65 |
Traffic Impacts: Lane closures and delays possible as part of a mobile operation. Date/Time: Daily – 8 p.m. to 5 a.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone. |
| |
|
| Franklin County |
|
| KY 12 (Flat Creek Road) |
Traffic Impacts: Overnight weekday closures. Date/Time: Nightly from 6 p.m. to 6 a.m. on weekdays beginning Thursday, Aug. 6, through Friday, Aug. 14. Project Limits: KY 12 (Flat Creek Road) from mile point 5.540 (near CR 1314/Harvieland Road) to mile point 7.5 (near Onans Bend Road). Type of Work: Base failure repairs ahead of an upcoming asphalt resurfacing project. Other Details: Local traffic will directed through the work zone via flagging operations. |
| KY 12 (Flat Creek Road) |
Traffic Impacts: N/A. Date/Time: Beginning Aug. 11, through the Fall of 2026. Project Limits: KY 12 bridge over Flat Creek at mile point 12.46 (at the Franklin/Henry County line). Type of Work: Bridge replacement project. Other Details: Traffic will be maintained on the existing bridge until construction has been completed on the replacement bridge. |
| U.S. 60 (Capital Avenue) Bridge |
Traffic Impacts: Lane closures on the bridge.
Date/Time: Daily/Nightly.
Project Limits: U.S. 60 (Capital Avenue) bridge over the Kentucky River.
Type of Work: Bridge maintenance project.
Detour: During the weekend closure, motorists should follow the signed detour route via KY 420 (Old Lawrenceburg Road, KY 676 (East-West Connector), KY 1659 (Martin Luther King Jr. Boulevard), and U.S. 60 (East Main Street) before reconnecting with U.S. 60 (Capital Avenue).
Other Details: The approximately $925,000 project will include placement of a latex concrete overlay, bridge rail repairs, pier maintenance, and sidewalk repairs. The improvements are designed to preserve the structure and extend its service life. The bridge was originally constructed in 1938.
|
| I-64 East and West |
TRAFFIC ADVISORY: Overnight alternating lane closures will occur nightly from 7 p.m. through 6 a.m. beginning Sunday, Aug. 16, through Friday, Aug. 21, on I-64 East and West between mile markers 53 and 58 (between U.S. 127 and U.S. 60). The overnight alternating lane closures are necessary for contract crews to apply a concrete overlay to the I-64 bridges over U.S. 60 (Versailles Road), install shoulder rumble strips, perform pavement striping and place pavement markers.
In addition to the overnight alternating lane closures on I-64 East and West, overnight alternating lane closures will be in place on U.S. 60 (Versailles Road) beneath the I-64 bridges at mile point 57.9 from 9 p.m. to 6 a.m. beginning Sunday, Aug. 16, through Friday, Aug. 21. Traffic Impacts: Lane closures and traffic shifts, and delays are possible. Date/Time: Daily/nightly beginning Thursday, Sept. 4. Project Limits: I-64 East and West, between the Frankfort exits (mile markers 53 and 58). Type of Work: The I-64 improvement project, between the Frankfort exits (mile markers 53 and 58), includes the milling and removal of the existing asphalt surface followed by resurfacing with new asphalt pavement. Other improvements to the 5-mile corridor include bridge repairs and bridge crash wall repairs. Other Details:
- U.S. 60 (Versailles Road):
U.S. 60 (Versailles Road) will be reduced to one lane in each direction under the I-64 overpass bridge nightly from 9 p.m. to 6 a.m. beginning Monday, Sept. 15, 2025.
|
| U.S. 127/Vandalay Drive Intersection |
Traffic Impacts: Lane closures and traffic shifts are possible. Date/Time: Daily from 9 a.m. to 3 p.m. Project Limits: U.S. 127/Vandalay Drive intersection. Type of Work: The scope of the project includes constructing a new roundabout at the intersection of Vandalay Drive and Westridge Drive; extending Vandalay Drive to Limestone Drive to create a direct connection to KY 676 (East-West Connector); extending Vandalay Drive to U.S. 127 near the I-64/U.S. 127 interchange; and adding dual receiving lanes to improve left-turn movements from U.S. 127 onto Westridge Drive. Other Details: The project is scheduled to be completed by the summer of 2026. |
| *Various Locations on I-64 |
Traffic Impacts: Lane closures and delays possible as part of a mobile operation. Date/Time: Daily – 8 p.m. to 5 a.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone. |
| |
|
| Oldham County |
|
| I-71 North |
Traffic Impacts: Closure of the right lane.
Date/Time: From 9 a.m. to 9 p.m. on Monday, Aug. 17.
Type of Work: Routine maintenance of the interstate.
Other Details: Motorists should heed signage and use caution when traveling through the work zone.
|
| KY 393/KY 146/Allen Lane |
Traffic Impacts: Lane closures are possible.
Date/Time: Daily/nightly.
Type of Work: Major infrastructure improvement project along KY 393, KY 146, and Allen Lane. The project includes reconstruction and realignment of KY 393 north of the I-71 interchange to KY 146 and Allen Lane from the Commerce Parkway/Ernie Harris Parkway intersection to KY 146, and the construction of two rail-over-road bridges to replace existing at-grade railroad crossings.
Additional improvements as part of the project include: - Widening and reconstruction of KY 393, including expanded travel lanes and turn lanes - Construction of a new KY 393 extension connecting to KY 146 - Widening and reconfiguration of Allen Lane from Commerce Parkway to KY 146 - Intersection improvements at Ernie Harris Parkway and Spring House Pike - Addition of dedicated turn lanes at KY 146 and Allen Lane
Other Details: Motorists are encouraged to slow down, remain alert, and follow all work zone signage and flagging personnel. Drivers should also expect changing conditions throughout construction. Additional project information and traffic updates will be provided as work progresses.
|
| *Various Locations |
Traffic Impacts: Lane closures and delays possible as part of a mobile operation.
Date/Time: Daily – 7 a.m. to 9 p.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone.
|
| *Various Locations on I-71 |
Traffic Impacts: Lane closures and delays possible as part of a mobile operation.
Date/Time: Daily – 8 p.m. to 5 a.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone.
|
| |
|
| Spencer County |
*Routine Maintenance* |
| |
|
| Shelby County |
|
| U.S. 60 East (Main Street) |
Traffic Impacts: Closure of the U.S. 60 East (Main Street) bridge. Date/Time: Beginning Monday, July 6, through Dec. 18. Project Limits: U.S. 60 East (Main Street) Bridge over Clear Creek. Type of Work: Bridge replacement project. Other Details: To ensure construction can be completed safely and efficiently, a closure of the U.S. 60 East (Main Street) bridge is scheduled to begin Monday, July 6. During the construction of the new bridge, two-way traffic will be shifted to the U.S. 60 West (Washington Street) bridge. The newly constructed bridge is expected to open to traffic on Friday, Dec. 18. |
| I-64 Widening and Improvement Project |
**Traffic impacts available here.**
|
| KY 55X/KY 43 |
Traffic Impacts: Daily lane closures are possible. Date/Time: Daily from 9 a.m. to 3 p.m. beginning on or after Monday, March 2. Project Limits: Intersection of KY 55X and KY 43. Type of Work: Intersection improvement project. Intersection improvements include upgrading the existing traffic signal, adding right-turn lanes on all approaches, and constructing dedicated left-turn lanes for northbound and southbound KY 55X. These enhancements will improve traffic flow, reduce delays, and enhance safety for motorists traveling through the corridor. Other Details: The project completion date anticipated for late this Summer. Additional project information is available online.
|
| *Various Locations on I-64 |
Traffic Impacts: Lane closures and delays possible as part of a mobile operation. Date/Time: Daily – 8 p.m. to 5 a.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone. |
| |
|
| Henry County |
|
| KY 55 (Eminence Road) |
Traffic Impacts: Daily road closures. Date/Time: Daily from 9 a.m. to 3 p.m. on Wednesday, Aug. 19, and Thursday, Aug. 20. Project Limits: KY 55 (Eminence Road) will be closed between mile point 1.4 (at the south end of KY 55) and mile point 4.49 (near the KY 55/U.S. 421 intersection). Type of Work: Routine bridge maintenance for bridges located at mile point 3.3 and 3.6. Other Details: A signed detour will be implemented at mile point 1.4 (at the south end of KY 55) and at mile point 4.49 (near the KY 55/U.S. 421 intersection). Drivers should plan to use KY 22 and U.S. 421 to detour around the affected area and allow for increased travel time. |
| *Various Locations on I-71 |
Traffic Impacts: Lane closures and delays possible as part of a mobile operation. Date/Time: Daily – 8 p.m. to 5 a.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone. |
| |
|
| Trimble County |
*Routine Maintenance* |
| *Various Locations on I-71 |
Traffic Impacts: Lane closures and delays possible as part of a mobile operation. Date/Time: Daily – 8 p.m. to 5 a.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone. |
We now have a new way for you to map crime around you. Just click here and view our new interactive crime mapping tool for Division 5 & 8 or for each beat in Division 5 & 8. And save it in your favorites to view crime anytime it's updated daily. On the page is a Quickfind tool that allows you to put your address in and subscribe to crime trends, alerts and block watch reports for your police beat. Forward this email to your friends and family!
For further information on Councilman Scott Reed or District 16 please visit www.louisvilleky.gov/government/metro-council-district-16
You can also reach out directly by phone at 502.574.1116 or by email at scott.reed@louisvilleky.gov.