Broadband Update -BROADBAND BUILDOUT ORDER - POWER SUPPLY INSTALLATION TO BEGIN IN 3 WEEKS
Louisville Metro Government sent this bulletin at 02/12/2024 08:12 PM ESTBROADBAND BUILD OUT ORDER
1 - BL11E - OLD TAYLORSVILLE ROAD AREA
2 - BL10E - SOUTH POPE LICK ROAD AREA
3 - BL20E - HOPEWELL ROAD AREA
4 - BL13E - OLD ROUTT ROAD/ROUTT ROAD AREA
5 - BL14E - TAYLORSVILLE LAKEROAD AREA
6 - VLO1E - BLEVINS GAP AREA
7 - BL15E - ECHO TRAIL AREA
8 - BL18E - DRY RIDGE ROAD AREA
9 - BL12E - OLD CLARK STATION AREA
10 - BLI6E - VISTA HILLS BLVD AREA
11 - WP68E - MINT SPRING AREA
12 - WP87E - JOHNSON ROAD AREA
13 - BL17E - BROAD RUN ROAD AREA
Please see attached map for area labels.
-
- Pole permits have been submitted for approval to LG&E- Approximately 146 poles (out of 2,198 total) have been approved to date ( this number is increasing daily) - - The first power supplies should be set within 2-3 weeks. A power supply will be needed in each boundary area to support the OLT placement.
- Spectrum is proactively submitting all other permits (railroad, highway, etc.) and have submitted 22 of the 33 necessary for the project in the hopes of having those expedited.
If you have any questions please contact the office at 574-1120 or reach out to me by email at stuart.benson@louisvilleky.gov.
