Blevins Gap Bridge Replacement Project Update

         The District 13 office received the following update from Matthew Haines, Metro Public Works Engineering Supervisor:

        Please see planned schedule for the bridge replacement on Blevins Gap Road.  The plan is to start in early October and complete the project in early December.  Please note that weather may have some impacts on schedule.  

Matthew R. Haines, PE, Engineering Supervisor, Louisville Metro Public Works & Assets, 502 574 3883 (D) I 502 574 4129 (F)

 

Blevins Gap Safety Improvements Project Timeline

OCTOBER

                10 – Remove guard rail

                10 - Install Creek Crossing

                13 – Demo bridge

                18 - Clear & Grub trees

                 24 - Form & pour #1 end & wings

                 27 - Form & pour #2 end & wings

NOVEMBER

                  7 - Embankment in place

                  7 - Set box beams

                  8 - Install inlet protection

                  9 - Pour wing walls

                11 - Tie deck reinforcing steel

                18 - Pour dreck

                24 - Seal Deck & Concrete

                23 - Mill asphalt

                28 -  Pave roadway

DECEMBER

                  1 -  Install guardrail

                   2 -  Striping

                   2 -  Address erosion control measures

                   2 -  REMOVE ROAD CLOSURE

Additional work occurring during project   Install, cut and tie in 12" watermain

 

December 2, 2022 Project Finish Date

( if  no weather delays occur during above timeline )