The District 13 office received the following update from Matthew Haines, Metro Public Works Engineering Supervisor:
Please see planned schedule for the bridge replacement on Blevins Gap Road. The plan is to start in early October and complete the project in early December. Please note that weather may have some impacts on schedule.
Matthew R. Haines, PE, Engineering Supervisor, Louisville Metro Public Works & Assets, 502 574 3883 (D) I 502 574 4129 (F)
Blevins Gap Safety Improvements Project Timeline
OCTOBER
10 – Remove guard rail
10 - Install Creek Crossing
13 – Demo bridge
18 - Clear & Grub trees
24 - Form & pour #1 end & wings
27 - Form & pour #2 end & wings
NOVEMBER
7 - Embankment in place
7 - Set box beams
8 - Install inlet protection
9 - Pour wing walls
11 - Tie deck reinforcing steel
18 - Pour dreck
24 - Seal Deck & Concrete
23 - Mill asphalt
28 - Pave roadway
DECEMBER
1 - Install guardrail
2 - Striping
2 - Address erosion control measures
2 - REMOVE ROAD CLOSURE
Additional work occurring during project Install, cut and tie in 12" watermain
December 2, 2022 Project Finish Date
( if no weather delays occur during above timeline )
|