This week, the contractor completed the remaining landscape restoration work on 143rd Street, Ridge Road, and Johnson Road. The streetlights along 143rd Street were provided with power and the system was turned on. Over the next two weeks, the contractor will address various punch list items and that will bring the project to full completion. |
|
 |