Renew the Avenue project – The electrical contractor will continue drilling, pouring and installing the new light pole and traffic signal foundations on Oak Park Ave. from Pleasant St. to South Blvd. through the end of next week. The roadway crew will continue framing and pouring roadway base course patches at various locations this week. The crew will also be preparing next week for the sidewalk excavation and ramp placement for pedestrian access between Pleasant and South Blvd. during the week of August 3rd. Access to all buildings and businesses on this block will be always maintained during this work period.
AT&T will be back onsite between North Blvd. and Lake St. installing a new communications manhole by the Hunters Court crossing. Union Pacific continues to complete concrete abutment repairs on the bridge overpass between South and North Boulevards on Oak Park Ave.
Don’t forget to check out the Village of Oak Park and Hemmingway District’s new Bike to the Biz promotion. For more details, click here.
Alley improvement project – Concrete and brick installations in the alley between the 200 blocks of S. Grove Ave. and S. Kenilworth Ave. are expected to be completed by the end of this week, with an anticipated opening by July 31.
Removals began in the alley between the 800 blocks of N. Harvey Ave. and Mapleton Ave. Removals are expected to be completed by July 27, with new concrete installations to follow. After the removals in this alley are completed, the roadway and alley patching work will begin throughout the project locations.
Rectangular Rapid Flashing Beacon (RRFB) installations – The contractor finished setting all the new RRFB’s this week. On Friday, they began adding the signage to the poles and activating them for use. This work will continue over the next several working days.
Water and sewer project – The contractor on Scoville continued installing the new sewer main on the 1100 S. block this week. Next, the contractor will begin replacing sewer services, which span from the new sewer main to the curb, for the next few weeks. Water main installation is expected to recommence after the sewer services on the block have been installed.
The contractor on Euclid installed the new sewer main on the 1100 N. block this week. They will continue sewer main installation next week, continuing north onto the 1200 N. block of Euclid Avenue.
Resurfacing project –The resurfacing contractor will be prioritizing the resurfacing locations near schools on the project first, which includes the Erie and Van Buren locations. Then, they plan to move through the Village from north to south completing the rest of the locations.
The work this week included starting to saw cutting pavement for removals and also lowering manholes at the Erie, Van Buren and Forest locations. Tree root pruning and concrete curb and sidewalk removals will begin next week at these locations.
|