|
Buffalo Grove Road from IL 22 to Aptakisic Road is almost complete! Asphalt paving and pavement striping is now complete. This week, crews plan on finishing landscape restoration, removing barricades, and other miscellaneous cleanup work.
LCDOT appreciates everyone’s patience throughout the construction season. We’re excited to say that all lanes of traffic are now open!
Traffic Impacts: Watch for workers and flaggers. Please be cautious of trucks coming in and out of the jobsite.
 Newly repainted Buffalo Grove Road
About the Project
Description: Buffalo Grove Road from Deerfield Pkwy to IL 22 will be completely reconstructed to provide two lanes of travel in each direction. This includes a center median and turn lanes at all major intersections. A new traffic signal will be installed at the intersection of Thompson Blvd. Crosswalks at each street crossing will be improved and upgraded to ADA standards.
Crews will also connect the bike path gap between Aptakisic Road and Brandywyn Lane making it easier for residents to walk and bike to local parks, schools and shopping areas.
Temporary lane closures may occur a few hours per day to complete major work.
Construction will take place over a two-year period using a staged approach:
-
North Section: Focused construction on Buffalo Grove Road from IL 22 to Aptakisic Road, with minor impacts south of Aptakisic.
-
South Section: Focused construction on Buffalo Grove Road from Aptakisic Road to Deerfield Pkwy. This includes intersection improvements at Buffalo Grove Road and Aptakisic Road, which will extend to slightly north of Aptakisic.
Project Website: lakecountyil.gov/buffalogroverd
|