Friday, July 10, 2026 | View in browser
Fleetwood-Jourdain Exterior Improvements
 |
Project Description
Over the next several months, the City of Evanston will be contracting for improvements at the Fleetwood Jourdain Community Center (1655 Foster Street). Work will include a new exterior patio space situated directly east of the community center.
Project Schedule
This project is anticipated to begin in July 2026 and be completed in September 2026. During construction, the exterior site immediately east of the Fleetwood-Jourdain Community Center will be closed to the public. Construction activities may cause some inconveniences for residents, but we will work to minimize them. Limited parking restrictions on adjacent roadways may be required to accommodate construction activities and will be posted with temporary “NO PARKING” signs 48 hours in advance.
Contractor
The project’s general contractor is Ampol Group International, Inc., 521 Santa Rosa Drive, Des Plaines, Illinois 60018
Project Monitoring
The project is monitored by the City’s Capital Planning & Engineering Bureau. If you have questions or concerns during construction, please get in touch with Stefanie Levine, Senior Project Manager, at 3-1-1 or 847-448-4311. View the bulletin in PDF format.
2026 Alley and Pedestrian Crossing Improvement Projects to Begin
 Project Description
The 2026 Alley and Pedestrian Crossing Improvements project will take place over the next five months. A summary of the project locations and scope of work is provided below:
|
Project
|
Scope
|
|
Alley North of Payne St, East of Hartrey Ave
|
Storm sewer installation, concrete pavement, and restoration.
|
|
Alley North of Clinton St, East of Orrington Ave
|
|
Alley North of Simpson St, East of Pioneer Rd
|
|
Dodge Ave and Foster St Pedestrian Crossing
|
Installation of concrete curb extensions, sidewalk removal and replacement, ADA ramps, solar-powered LED pedestrian crossing signs with push buttons, in-street signs, and striping.
|
|
Emerson St and Dewey Ave Pedestrian Crossing
|
Improvements to existing pedestrian crossings, including sidewalk removal and replacement, ADA ramps, installation of solar-powered LED pedestrian crossing signs with push buttons, and striping.
Improvements to the existing pedestrian crossing, including installation of a concrete median, sidewalk removal and replacement, ADA ramps, RRFB pedestrian and bike crossing signs with push buttons, and striping.
|
|
Emerson St and Hartrey Ave Pedestrian Crossing
McCormick Blvd and Prairie Avenue Pedestrian Crossing
|
|
Traffic Calming - Speed Humps and Alley Bumps
|
Installation of traffic-calming speed humps and alley speed bumps at various locations.
|
Project Schedule
The project is expected to begin within the next two weeks and be completed by November 20. Because construction will take place at multiple locations, affected residents will receive a construction notice before work begins in their area. Each notice will provide the anticipated construction schedule, any temporary parking restrictions, and other important project information.
Contractor
The contractor for this project is Zenith Construction and Engineering Services LLC (2608 W. Van Buren St., Chicago, IL 60612).
City Contact
This project will be monitored by the City’s Capital Planning & Engineering Bureau. If you have any questions or concerns during construction, please do not hesitate to contact the Resident Engineer, Charlie Oppliger, at (224) 630-5381. Questions about the project in general should be directed to Chris Sous, Assistant City Engineer, at (847) 859-7835 or csous@cityofevanston.org. View the bulletin in PDF format.
|