City to Begin Pavement Patching on Elgin Road and Orrington Avenue the Week of July 20

The City of Evanston will be patching large areas of asphalt pavement on Elgin Road from Benson Avenue to Orrington Avenue and on Orrington Avenue from Davis Street to Clark Street beginning the week of July 20. The work is scheduled to be completed by July 24, weather permitting, as part of the 2020 Motor Fuel Tax Street Resurfacing Project.

This project will entail removing the top distressed and failing asphalt surface and replacing it with a fresh, smooth asphalt surface coarse material. 

During construction, motorists should expect minor delays near work zones as flaggers route traffic around the work crews. Traffic will be maintained on Elgin Road and Orrington Avenue during street grinding and asphalt patching operations. "No Parking" restrictions should be short in duration and specific to the daily work zones. "No Parking" signs will be posted 48 hours in advance of when the restriction is enforced and will be removed as soon as the work is completed.

Contractor
The contractor for this project is J.A. Johnson Paving, 1025 E. Addison Court, Arlington Heights, IL 60005.

City Monitoring
The project is under the supervision of the City’s Capital Planning & Engineering Bureau. For questions or concerns regarding this project, please contact Resident Engineer Pankaj Chokshi at 224-723-8237. For questions about the street resurfacing project in general, contact Senior Project Manager Sat Nagar, P.E., at 847-448-4311.