City of Evanston Provides Capital Improvement Projects Update
EVANSTON, ILLINOIS - The City of
Evanston's Public Works Agency is providing community members with an update on major Capital Improvement
Program (CIP) projects taking place throughout the city.
Sheridan Road/Chicago
Avenue
Work has resumed on the Sheridan Road/Chicago Avenue improvement project after
the project was temporarily shut down due to the State’s budget issues. This
week, Phase 2 of the project resumes, which includes Sheridan Road from the
Chicago Avenue/Sheridan Road intersection to Lincoln Street. Traffic is being
shifted to the east side of Sheridan Road so that the reconstruction of the
road base on the west side can begin. Once construction of the west side of
Sheridan Road is complete, traffic will be switched onto the new lanes to
accommodate road construction on the east side. Originally, all Phase 2 work was
expected to be complete by September 15, but this is now unlikely because critical time was lost during the State-directed project shutdown. This stretch
of construction is expected to be completed sometime in the fall.
Phase 1 of the project, which includes Chicago Avenue from
Grove Street to the Chicago Avenue/Sheridan Road intersection, was completed in
June. In specific locations, reflectors will be added to protected bike lane curbs to improve visibility. Phase 3, from Lincoln Street to Ridge Avenue,
is expected to proceed on schedule in 2018.
Emerson/Ridge/Green
Bay Project
Additional directional signage is scheduled to be installed at the Emerson
Street, Ridge Avenue and Green Bay Road intersection in late summer, and traffic
signal timing continues to be periodically modified. The contractor is completing the final list
of items needed to close out the contract.
Fountain Square
Progress on Fountain Square improvements continues. Substantial water main,
sewer and other underground utility work has been completed, and sidewalks
south of Davis Street are almost complete. The new plaza south of Davis Street
is expected to be complete this fall. North of Davis Street, work has been
proceeding, but issues with underground utilities and longer than expected lead
times for the veterans memorial wall and the fountain are resulting in some
delays. The impact is not currently known, but the north plaza construction may
extend into the spring of 2018.
Penny Park
Penny Park celebrated its grand reopening on Memorial Day weekend, with many
Evanston residents celebrating the return of the beloved playground. Some
additional landscaping work remains and will be completed in the fall when
conditions are better for planting. Meanwhile, caregivers and children are
advised to use caution when enjoying metal slides at Penny Park and other City playgrounds
on sunny days, as the metal can be hotter than expected. Additional signage has
been installed to remind park users to exercise caution.
The City of Evanston thanks residents for their patience
during the busy construction season. As always, community members are advised
to take special care when entering a work zone, both for their safety and the
safety of construction workers.
Additional information about all of Evanston’s capital
improvement projects can be found on the City's website at cityofevanston.org/cip, or by
calling/texting 847-448-4311. For convenience, residents may simply dial 3-1-1
in Evanston.